7633 N FALLBROOK AVE 91304

Certificate Information: 7633 N FALLBROOK AVE 91304

Application / Permit
23010-20000-03753
Plan Check / Job No.
B23VN12703
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. New detached one-story ADU, 1191 sq.ft. Per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 2/6/2024
Issuing Office
Current Status
CofO Issued on 6/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2023 APPLICANT
Assigned to Plan Check Engineer 9/22/2023 ALFREDO JARA
Corrections Issued 9/25/2023 ALFREDO JARA
Applicant returned to address corrections 10/20/2023 ALFREDO JARA
Applicant returned to address corrections 11/7/2023 AMY GUEVARRA
Applicant returned to address corrections 12/14/2023 AMY GUEVARRA
Plan Check Approved 1/26/2024 ALFREDO JARA
Issued 2/6/2024 APPLICANT
CofO in Progress 3/17/2025 JEFFREY HARTLINE
Permit Finaled 6/23/2025 JOHN JANSON
CofO Issued 6/23/2025 JOHN JANSON
Permit Finaled 6/23/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/3/2023 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 10/3/2023 MARKOS PEREZ-BRAN
Sewer availability Cleared 10/3/2023 MARKOS PEREZ-BRAN
Low Impact Development (LID) Cleared 12/5/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 12/18/2023 CARLOS AGUILERA
Miscellaneous Cleared 1/17/2024 EDGAR ALCARAZ
Construction within easement Cleared 1/20/2024 RIDWAN HARDY

Contact Information

Contractor Tritech Construction; Lic. No.: 556536-B       ,
Engineer Azarbin,, Hamid; Lic. No.: C64515 22655 COVELLO ST      WEST HILLS, CA 91307

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/6/2024 Approved JEFFREY HARTLINE
PLUMBING-Rough 3/20/2024 Partial Approval JEFFREY HARTLINE
Pre-Inspection 3/20/2024 Partial Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 3/26/2024 Partial Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 5/14/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 6/21/2024 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 6/26/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 6/26/2024 Approved JEFFREY HARTLINE
Green Building Rough 6/26/2024 Approved JEFFREY HARTLINE
HVAC-Rough 6/26/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 6/26/2024 Partial Approval JEFFREY HARTLINE
Verify Sprinkler Sign Off 6/26/2024 Approved JEFFREY HARTLINE
Insulation 7/3/2024 Approved JEFFREY HARTLINE
Drywall Nailing 7/11/2024 Approved JEFFREY HARTLINE
Shower Pan 7/31/2024 Approved GEVORK IPCHYAN
Underground Mechanical 10/9/2024 Approved JEFFREY HARTLINE
Service/Power Release 11/13/2024 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Final 1/27/2025 Not Ready for Inspection JEFFREY HARTLINE
Final 1/27/2025 Corrections Issued JEFFREY HARTLINE
HVAC-Final 1/27/2025 Approved JEFFREY HARTLINE
PLUMBING-Final 1/27/2025 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Not Required JEFFREY HARTLINE
Service/Power Release 1/27/2025 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 1/27/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Final 3/3/2025 Approved JEFFREY HARTLINE
Final 3/3/2025 Partial Approval JEFFREY HARTLINE
Service/Power Release 3/3/2025 Approved JEFFREY HARTLINE
Special/Order Compliance 3/11/2025 Corrections Issued JEFFREY HARTLINE
Final 3/18/2025 OK to Issue CofO JEFFREY HARTLINE