1040-1040 1/2 E 53RD ST 90011
Certificate Information: 1040-1040 1/2 E 53RD ST 90011
- Application / Permit
- 23010-20000-03731
- Plan Check / Job No.
- B23VN11418
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW IRR. SHAPED 29'-3 1/2" x 22'-10 1/2" DET. TWO STORY ACCESSORY BLDG (2 ADUs, ONE AT EACH LEVEL) PER CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)); NFPA-13D THRU-OUT
- Permit Issued
- Issued on 5/16/2024
- Issuing Office
- Current Status
- CofO Issued on 9/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2023 | SEAN SHAHMIRI |
| Corrections Issued | 9/18/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 9/22/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 10/27/2023 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 11/21/2023 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 5/7/2024 | SEAN SHAHMIRI |
| Plan Check Approved | 5/9/2024 | SEAN SHAHMIRI |
| Issued | 5/16/2024 | APPLICANT |
| CofO in Progress | 9/5/2025 | ALEJANDRO DE ARTOLA |
| CofO Issued | 9/8/2025 | DEROLD HAUFF |
| Permit Finaled | 9/8/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 11/9/2023 | GILBERT URREA |
| Address approval | Cleared | 2/5/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2024 | CELINA MORENO |
| Sewer availability | Cleared | 2/16/2024 | CELINA MORENO |
| Low Impact Development (LID) | Cleared | 4/16/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 4/17/2024 | CELINA MORENO |
Contact Information
| Architect | Knight,, Brian Frederick; Lic. No.: C32905 | 1337 LIDA STREET PASADENA, CA 91103 |
| Contractor | Good News Construction Inc; Lic. No.: 967654-B | P O BOX 570679 LOS ANGELES, CA 91357 |
| Engineer | Phan,, Phillip Trung Tri; Lic. No.: C76425 | 641 S ALMIRANTE DR WEST COVINA, CA 91791 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/10/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 6/20/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 6/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 6/26/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 6/27/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/5/2024 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/22/2024 | Partial Approval | MICHAEL LEWIS |
| Sewer | 8/22/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/5/2024 | Conditional Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 9/5/2024 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 9/5/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/11/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 9/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 9/13/2024 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 9/13/2024 | Partial Approval | ANTHONY RAMOS |
| Underground Mechanical | 12/26/2024 | Partial Approval | JOHN QUINTANILLA |
| Underground Mechanical | 1/7/2025 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 2/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/28/2025 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 3/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 3/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 3/12/2025 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 3/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 3/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/7/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 5/7/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 5/7/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Service/Power Release | 5/7/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 5/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 5/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 6/2/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/2/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 6/2/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 6/2/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 6/2/2025 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 6/2/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/22/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Final | 7/29/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 9/4/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| HVAC-Final | 9/4/2025 | Approved | ALEJANDRO DE ARTOLA |