7945 N BELLAIRE AVE 91605
Certificate Information: 7945 N BELLAIRE AVE 91605
- Application / Permit
- 23010-20000-03725
- Plan Check / Job No.
- B23VN12598
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW 22'-6" x 33'-10" TWO-STORY ACCESSORY LIVING QUARTERS; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 8/19/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | SEAN SHAHMIRI |
| Corrections Issued | 10/5/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 10/13/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 10/17/2023 | APPLICANT |
| Applicant returned to address corrections | 1/11/2024 | SEAN SHAHMIRI |
| Plan Check Approved | 1/11/2024 | SEAN SHAHMIRI |
| No Progress | 1/11/2024 | SEAN SHAHMIRI |
| Plan Check Approved | 8/15/2024 | SEAN SHAHMIRI |
| Issued | 8/19/2024 | APPLICANT |
| CofO in Progress | 2/27/2026 | VINCENT HANLEY |
| CofO Issued | 3/26/2026 | RUBEN SALAS |
| Permit Finaled | 3/26/2026 | RUBEN SALAS |
Permit Application Clearance Information
| "T" removal | Cleared | 10/17/2023 | ALEX VELA |
| ZA Case | Cleared | 10/17/2023 | ALEX VELA |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/18/2023 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 11/17/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/18/2023 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 12/23/2023 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Andrejic,, Milos; Lic. No.: C67443 | 3601 BEVERLY RIDGE DR SHERMAN OAKS, CA 91423 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/16/2024 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 9/18/2024 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/18/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 9/25/2024 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/25/2024 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/18/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 10/18/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 10/18/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 10/18/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Deputy Wood Construction | 10/21/2024 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Partial Approval | DAVID MATSON |
| Deputy Wood Construction | 11/22/2024 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2024 | Partial Approval | GREGG CUMMINGS |
| Wood Frame | 11/25/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Approved | DAVID MATSON |
| ELECTRICAL-Rough | 12/20/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 12/20/2024 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 12/20/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/2/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 1/2/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 1/2/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/2/2025 | Partial Approval | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 1/2/2025 | Approved | VINCENT HANLEY |
| Insulation | 1/8/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/8/2025 | Approved | VINCENT HANLEY |
| Shower Pan | 1/8/2025 | Approved | VINCENT HANLEY |
| Drywall Nailing | 1/21/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 12/5/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 12/5/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/5/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Service/Power Release | 12/5/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Smoke Detectors | 12/5/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 1/29/2026 | Corrections Issued | VINCENT HANLEY |
| Final | 1/29/2026 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 1/29/2026 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 1/29/2026 | SGSOV Not Required | VINCENT HANLEY |
| Service/Power Release | 1/29/2026 | Approved | VINCENT HANLEY |
| Smoke Detectors | 1/29/2026 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 2/6/2026 | Approved | VINCENT HANLEY |
| Final | 2/6/2026 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 2/6/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 2/6/2026 | Approved | VINCENT HANLEY |
| Final | 2/25/2026 | OK to Issue CofO | VINCENT HANLEY |