7149 W APPERSON ST 1-2 91042

Certificate Information: 7149 W APPERSON ST 1-2 91042

Application / Permit
23010-20000-03711
Plan Check / Job No.
B23VN12567
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(2) NEW DETACHED 2-STORY ADUs (32'-0"x28'-0"), 1580 SQFT PER CA GOVT CODE 65852.2(e)(1)(D) AND LAMC 12.22 A.33 (c)(d)(g)
Permit Issued
Issued on 1/3/2024
Issuing Office
Current Status
CofO Issued on 2/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2023 APPLICANT
Assigned to Plan Check Engineer 9/28/2023 PETER MOSESIAN
Corrections Issued 10/3/2023 PETER MOSESIAN
Quality Review Completed 10/11/2023 OMID HEDAYAT
Plan Check Approved 11/15/2023 PETER MOSESIAN
Issued 1/3/2024 APPLICANT
CofO in Progress 2/12/2025 WILLIAM WREN
Permit Finaled 2/12/2025 RUBEN SALAS
CofO Issued 2/12/2025 RUBEN SALAS
Permit Finaled 2/12/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/6/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/6/2023 COLIN LOREDO
Highway dedication Cleared 10/6/2023 PETER MOSESIAN
Frnt yard landscape/Water mgmt Cleared 10/7/2023 STEVEN WECHSLER
Hydrant and Access approval Cleared 10/12/2023 LAVEON RIDER
Specific Plan Cleared 10/18/2023 ERICK MARCHENA
ZI Cleared 10/18/2023 ERICK MARCHENA
Sewer availability Cleared 10/25/2023 ROSE MARIE SMITH
Low Impact Development (LID) Cleared 10/26/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 10/30/2023 COLIN LOREDO
GPI Written Notices Cleared 11/15/2023 PETER MOSESIAN
Grading Pre-Inspection Cleared 11/15/2023 PETER MOSESIAN

Contact Information

Contractor V And H Construction Inc; Lic. No.: 1110649-B       ,
Engineer Moradian,, Helbert; Lic. No.: C76618 6854 FOOTHILL BLVD      TUJUNGA, CA 91042

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/31/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 2/7/2024 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 2/21/2024 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 2/29/2024 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 3/20/2024 Partial Approval WILLIAM WREN
Green Building Rough 3/20/2024 Not Ready for Inspection WILLIAM WREN
Verify Sprinkler Sign Off 3/20/2024 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 4/9/2024 Corrections Issued WILLIAM WREN
Sewer 5/30/2024 Approved WILLIAM WREN
Underground Mechanical 5/30/2024 Partial Approval WILLIAM WREN
ELECTRICAL-Rough 6/3/2024 Not Ready for Inspection WILLIAM WREN
Underground Mechanical 6/3/2024 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 7/18/2024 Approved WILLIAM WREN
PLUMBING-Rough 7/18/2024 Approved WILLIAM WREN
BUILDING-Rough-Frame 7/19/2024 Approved WILLIAM WREN
ELECTRICAL-Final 7/19/2024 Approved WILLIAM WREN
Green Building Rough 7/19/2024 Approved WILLIAM WREN
HVAC-Rough 7/19/2024 Corrections Issued WILLIAM WREN
Insulation 8/6/2024 Conditional Approval WILLIAM WREN
Interior/Exterior Lathing 8/6/2024 Approved WILLIAM WREN
Drywall Nailing 8/13/2024 Approved WILLIAM WREN
Interior/Exterior Lathing 8/21/2024 Not Ready for Inspection WILLIAM WREN
Interior/Exterior Lathing 8/23/2024 Approved WILLIAM WREN
Shower Pan 8/29/2024 Approved WILLIAM WREN
ELECTRICAL-Final 12/26/2024 Not Ready for Inspection WILLIAM WREN
Service/Power Release 12/26/2024 Not Ready for Inspection WILLIAM WREN
Final 1/6/2025 Corrections Issued WILLIAM WREN
Green Building Final 1/6/2025 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 1/6/2025 SGSOV Not Required WILLIAM WREN
Service/Power Release 1/6/2025 Not Ready for Inspection WILLIAM WREN
Smoke Detectors 1/6/2025 Approved WILLIAM WREN
Final 1/17/2025 OK to Issue CofO WILLIAM WREN
Service/Power Release 1/17/2025 Approved WILLIAM WREN