12744 W BLYTHE ST 91605
Certificate Information: 12744 W BLYTHE ST 91605
- Application / Permit
- 23010-20000-03697
- Plan Check / Job No.
- B23VN12528
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 38' X 18' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 1/23/2024
- Issuing Office
- Current Status
- CofO Issued on 12/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | SELLA BENYAMIN |
| Corrections Issued | 10/5/2023 | SELLA BENYAMIN |
| Quality Review Completed | 10/6/2023 | STEVEN KIM |
| Building Plans Picked Up | 10/6/2023 | APPLICANT |
| Plan Check Approved | 1/23/2024 | SELLA BENYAMIN |
| Issued | 1/23/2024 | APPLICANT |
| CofO in Progress | 12/9/2024 | VINCENT HANLEY |
| Permit Finaled | 12/31/2024 | RUBEN SALAS |
| CofO Issued | 12/31/2024 | RUBEN SALAS |
| Permit Finaled | 12/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/30/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 11/3/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 11/13/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 11/14/2023 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 12/14/2023 | RIDWAN HARDY |
| Hold | Cleared | 2/16/2024 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/23/2024 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 2/27/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Underground Mechanical | 2/28/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 3/5/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 3/8/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 3/12/2024 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2024 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/16/2024 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 4/16/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 4/16/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 4/16/2024 | Corrections Issued | GREGG CUMMINGS |
| MERV13>=Rough | 4/16/2024 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 4/16/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 4/26/2024 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 4/26/2024 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 4/26/2024 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/1/2024 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/7/2024 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 5/7/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 5/7/2024 | Corrections Issued | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 5/7/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2024 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 5/10/2024 | Approved | GREGG CUMMINGS |
| Wood Frame | 5/10/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/14/2024 | Approved | GREGG CUMMINGS |
| Green Building Rough | 5/14/2024 | Approved | GREGG CUMMINGS |
| Sewer | 5/14/2024 | Approved | GREGG CUMMINGS |
| Shower Pan | 5/14/2024 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 5/14/2024 | Approved | GREGG CUMMINGS |
| Insulation | 5/20/2024 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 5/20/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 5/22/2024 | Approved | LEONARD ROSS II |
| Drywall Nailing | 5/24/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 5/24/2024 | Partial Approval | GREGG CUMMINGS |
| Interior/Exterior Lathing | 5/29/2024 | Partial Approval | GREGG CUMMINGS |
| Final | 8/6/2024 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/6/2024 | Approved | GREGG CUMMINGS |
| Green Building Final | 8/6/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| MERV13>=Final | 8/6/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/6/2024 | SGSOV Not Required | GREGG CUMMINGS |
| Service/Power Release | 8/6/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 8/6/2024 | Approved | GREGG CUMMINGS |
| Final | 9/6/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 9/6/2024 | Approved | VINCENT HANLEY |
| Service/Power Release | 9/6/2024 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Final | 11/27/2024 | Approved | GREGG CUMMINGS |
| Final | 11/27/2024 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Final | 11/27/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 11/27/2024 | Approved | GREGG CUMMINGS |
| Service/Power Release | 11/27/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 12/9/2024 | OK to Issue CofO | VINCENT HANLEY |
| Service/Power Release | 12/9/2024 | Approved | VINCENT HANLEY |