15329 W WYANDOTTE ST 91406
Certificate Information: 15329 W WYANDOTTE ST 91406
- Application / Permit
- 23010-20000-03674
- Plan Check / Job No.
- B23VN12438
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- EPLAN. NEW COVERED BARBEQUE AREA W/ PATIO COVER PER STANDARD PLAN IB P/BC 2017-009
- Permit Issued
- Issued on 10/31/2023
- Issuing Office
- Current Status
- CofO Issued on 3/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2023 | JASON JANGADA |
| Corrections Issued | 9/13/2023 | JASON JANGADA |
| Applicant returned to address corrections | 9/23/2023 | DAVID CASTILLO |
| Plan Check Approved | 10/15/2023 | DAVID CASTILLO |
| Issued | 10/31/2023 | APPLICANT |
| CofO in Progress | 2/9/2025 | VINCENT HANLEY |
| Permit Finaled | 3/15/2025 | RUBEN SALAS |
| CofO Issued | 3/15/2025 | RUBEN SALAS |
| Permit Finaled | 3/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2023 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 9/21/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | G N L Development Inc; Lic. No.: 981677-B | 5939 TOPEKA DRIVE TARZANA, CA 91356 |
| Engineer | Gharai,, Armin; Lic. No.: C61464 | 6701 CORIE LN WEST HILLS, CA 91307 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/27/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 9/27/2024 | Approved | VINCENT HANLEY |
| Gas Test | 9/27/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 9/27/2024 | Approved | VINCENT HANLEY |
| Sewer | 9/27/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 9/30/2024 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 9/30/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 9/30/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 9/30/2024 | Approved | VINCENT HANLEY |
| Gas Test | 11/7/2024 | Corrections Issued | VINCENT HANLEY |
| Service/Power Release | 11/7/2024 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/21/2025 | Partial Approval | VINCENT HANLEY |
| Final | 1/21/2025 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Final | 1/21/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 1/21/2025 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 1/21/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 1/21/2025 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 1/21/2025 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/27/2025 | Approved | VINCENT HANLEY |
| Final | 1/27/2025 | Not Ready for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 1/27/2025 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Final | 2/6/2025 | Approved | VINCENT HANLEY |
| Final | 2/6/2025 | OK to Issue CofO | VINCENT HANLEY |