6246 N SATSUMA AVE 91606
Certificate Information: 6246 N SATSUMA AVE 91606
- Application / Permit
- 23010-20000-03672
- Plan Check / Job No.
- B23VN12432
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 36' x 19' DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)1, (d)1, and (g). WORK PER WFPP.
- Permit Issued
- Issued on 4/17/2024
- Issuing Office
- Current Status
- CofO Issued on 12/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2023 | ISIS ARGUETA |
| Corrections Issued | 9/19/2023 | ISIS ARGUETA |
| Plan Check Approved | 4/17/2024 | ALEC MOUSAKHANIAN |
| Issued | 4/17/2024 | APPLICANT |
| CofO in Progress | 12/2/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 12/26/2025 | RUBEN SALAS |
| CofO Issued | 12/26/2025 | RUBEN SALAS |
| Permit Finaled | 12/26/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Hold | Cleared | 9/19/2023 | MARIA VENDIVIL |
| Address approval | Cleared | 10/5/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 10/10/2023 | COLIN LOREDO |
| Construction near power lines | Cleared | 2/8/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 3/19/2024 | PATRICK LOPEZ |
| Roof/Waste drainage to street | Cleared | 3/26/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/16/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Grading Pre-Inspection | 5/16/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 5/24/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 5/24/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 6/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 6/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 6/25/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 6/25/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Insulation | 7/3/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/24/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 7/24/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 8/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 8/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/21/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/21/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 8/21/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 9/3/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 9/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 9/3/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 9/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 9/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 9/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 9/16/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Sewer | 10/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 10/10/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 10/22/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 10/22/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 10/22/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 10/31/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 2/12/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 2/12/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/12/2025 | SGSOV Not Required | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 2/12/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 2/12/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 8/26/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 8/26/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 11/12/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 11/12/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 11/12/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 11/18/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 11/18/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 12/2/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 12/2/2025 | Approved | ROBERTO PALACIOS-LOPEZ |