20350 W SHERMAN WAY 91306
Certificate Information: 20350 W SHERMAN WAY 91306
- Application / Permit
- 23010-20000-03666
- Plan Check / Job No.
- B23VN11269
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan NEW DET. ADU PER LAMC 12.22 A.33 (c)-(d) -BLDG SPRINKLERED THRU-OUT "COMPLY WITH DEPARTMENT ORDER effective date 02/15/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 6/13/2024
- Issuing Office
- Current Status
- CofO Issued on 1/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/7/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 9/16/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 9/27/2023 | TU HUA |
| Applicant returned to address corrections | 3/21/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 5/19/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 6/3/2024 | MAHNAZ NOURHASHEMI |
| Issued | 6/13/2024 | APPLICANT |
| CofO in Progress | 12/3/2025 | JOEL GUARDADO |
| Permit Finaled | 1/13/2026 | DAVID JAMES |
| CofO Issued | 1/13/2026 | DAVID JAMES |
| Permit Finaled | 1/13/2026 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 11/20/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 11/20/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 2/14/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 2/14/2024 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 3/2/2024 | RUEL COLE |
| ZI | Cleared | 4/4/2024 | ALEX VELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kiledjian,, George Zohrab; Lic. No.: C74761 | 11447 VIKING AVE NORTHRIDGE, CA 91326 |
Inspector Information
| JACK UPCHURCH, (818) 374-9853 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/10/2024 | Approved | JOEL GUARDADO |
| Footing/Foundation/Slab | 9/10/2024 | Approved | JOEL GUARDADO |
| PLUMBING-Rough | 9/10/2024 | Approved | JOEL GUARDADO |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2024 | Approved | JOEL GUARDADO |
| Wood Frame | 10/4/2024 | Approved | JOEL GUARDADO |
| ELECTRICAL-Rough | 12/5/2024 | Approved | JOEL GUARDADO |
| HVAC-Rough | 12/5/2024 | Approved | JOEL GUARDADO |
| PLUMBING-Rough | 12/5/2024 | Not Ready for Inspection | JOEL GUARDADO |
| Interior/Exterior Lathing | 12/23/2024 | Approved | JOEL GUARDADO |
| PLUMBING-Rough | 12/23/2024 | Approved | JOEL GUARDADO |
| Wood Frame | 12/23/2024 | Approved | JOEL GUARDADO |
| PLUMBING-Rough | 12/31/2024 | Approved | JOEL GUARDADO |
| Wood Frame | 12/31/2024 | Approved | JOEL GUARDADO |
| Insulation | 1/14/2025 | Approved | JOEL GUARDADO |
| Drywall Nailing | 1/23/2025 | Approved | JOEL GUARDADO |
| Interior/Exterior Lathing | 3/19/2025 | Approved | JOEL GUARDADO |
| Sewer | 4/11/2025 | No Access for Inspection | JOEL GUARDADO |
| Sewer | 5/8/2025 | Approved | JOEL GUARDADO |
| Underground Mechanical | 5/9/2025 | No Access for Inspection | JOEL GUARDADO |
| ELECTRICAL-Final | 8/7/2025 | Approved | JOEL GUARDADO |
| HVAC-Final | 8/7/2025 | Partial Inspection | JOEL GUARDADO |
| PLUMBING-Final | 8/7/2025 | Partial Inspection | JOEL GUARDADO |
| BUILDING-Rough-Frame | 10/21/2025 | Not Ready for Inspection | MARIYA MIHALEVA |
| Final | 10/21/2025 | Not Ready for Inspection | MARIYA MIHALEVA |
| Green Building Final | 10/21/2025 | Not Ready for Inspection | MARIYA MIHALEVA |
| Green Building Rough | 10/21/2025 | Not Ready for Inspection | MARIYA MIHALEVA |
| SGSOV-Seismic Gas S/O Valve | 10/21/2025 | SGSOV Not Ready | MARIYA MIHALEVA |
| Service/Power Release | 10/21/2025 | No Access for Inspection | MARIYA MIHALEVA |
| Smoke Detectors | 10/21/2025 | Not Ready for Inspection | MARIYA MIHALEVA |
| Verify Sprinkler Sign Off | 10/21/2025 | Not Ready for Inspection | MARIYA MIHALEVA |
| BUILDING-Rough-Frame | 12/2/2025 | Approved | JOEL GUARDADO |
| Final | 12/2/2025 | OK to Issue CofO | JOEL GUARDADO |
| Green Building Final | 12/2/2025 | Approved | JOEL GUARDADO |
| Green Building Rough | 12/2/2025 | Approved | JOEL GUARDADO |
| SGSOV-Seismic Gas S/O Valve | 12/2/2025 | SGSOV Approved | JOEL GUARDADO |
| Service/Power Release | 12/2/2025 | Approved | JOEL GUARDADO |
| Smoke Detectors | 12/2/2025 | Approved | JOEL GUARDADO |
| Verify Sprinkler Sign Off | 12/2/2025 | Approved | JOEL GUARDADO |