1316-1318 W 61ST ST 90044

Certificate Information: 1316-1318 W 61ST ST 90044

Application / Permit
23010-20000-03663
Plan Check / Job No.
B23VN12382
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
eplan NEW 87'6" X 27' TWO STORY DUPLEX & ATTACHED 2-CAR GARAGE AND (1) CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQUIRED THOUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 2/20/2024
Issuing Office
Current Status
CofO Issued on 11/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2023 APPLICANT
Assigned to Plan Check Engineer 9/21/2023 RARES BODEA
Corrections Issued 9/28/2023 RARES BODEA
Quality Review Completed 10/3/2023 STEVEN KIM
Applicant returned to address corrections 1/8/2024 RARES BODEA
Plan Check Approved 1/18/2024 RARES BODEA
Issued 2/20/2024 APPLICANT
CofO in Progress 9/27/2024 CRAIG DAVIS
Permit Finaled 11/10/2024 DEROLD HAUFF
CofO Issued 11/10/2024 DEROLD HAUFF
Permit Finaled 11/10/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/27/2023 TREVOR QUAN
Permit Cleared 10/27/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 11/3/2023 TREVOR QUAN
Sewer availability Cleared 11/3/2023 TREVOR QUAN
Trees in Parkway Cleared 11/13/2023 ADALBERTO VERA
Low Impact Development (LID) Cleared 11/16/2023 SARAH YOUSSEF
Hydrant and Access approval Cleared 11/17/2023 KURT CORRAL
ZI Cleared 11/22/2023 YINGSHI HUANG
Roof/Waste drainage to street Cleared 11/28/2023 TREVOR QUAN

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/19/2024 Approved CRAIG DAVIS
Underground Mechanical 4/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 4/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/12/2024 Corrections Issued CRAIG DAVIS
Underground Mechanical 4/12/2024 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 4/16/2024 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 4/16/2024 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 4/17/2024 Partial Approval CRAIG DAVIS
Insulation 4/17/2024 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Approved CRAIG DAVIS
HVAC-Rough 6/20/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 6/20/2024 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 6/21/2024 Approved CRAIG DAVIS
ELECTRICAL-Rough 6/21/2024 Approved CRAIG DAVIS
Green Building Rough 6/21/2024 Approved CRAIG DAVIS
PLUMBING-Rough 6/21/2024 Approved CRAIG DAVIS
Verify Sprinkler Sign Off 6/21/2024 Approved CRAIG DAVIS
Insulation 6/24/2024 Approved CRAIG DAVIS
Drywall Nailing 7/5/2024 Approved CRAIG DAVIS
Interior/Exterior Lathing 7/5/2024 Approved CRAIG DAVIS
ELECTRICAL-Final 8/13/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Final 9/13/2024 Corrections Issued CRAIG DAVIS
Final 9/13/2024 Corrections Issued CRAIG DAVIS
Green Building Final 9/13/2024 Corrections Issued CRAIG DAVIS
HVAC-Final 9/13/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Final 9/13/2024 Corrections Issued CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 9/13/2024 SGSOV Not Ready CRAIG DAVIS
Service/Power Release 9/13/2024 Corrections Issued CRAIG DAVIS
Smoke Detectors 9/13/2024 Approved CRAIG DAVIS
ELECTRICAL-Final 9/17/2024 Partial Approval CRAIG DAVIS
Final 9/17/2024 Partial Inspection CRAIG DAVIS
HVAC-Final 9/17/2024 Partial Approval CRAIG DAVIS
PLUMBING-Final 9/17/2024 Partial Approval CRAIG DAVIS
Final 9/23/2024 Corrections Issued ANTHONY EGSON
Green Building Final 9/23/2024 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 9/23/2024 SGSOV Approved ANTHONY EGSON
Service/Power Release 9/23/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 9/26/2024 Approved CRAIG DAVIS
Final 9/26/2024 OK to Issue CofO CRAIG DAVIS
Green Building Final 9/26/2024 Approved CRAIG DAVIS
HVAC-Final 9/26/2024 Approved CRAIG DAVIS
PLUMBING-Final 9/26/2024 Approved CRAIG DAVIS
Service/Power Release 9/26/2024 Approved CRAIG DAVIS