19115-19119 W STAGG ST 91335
Certificate Information: 19115-19119 W STAGG ST 91335
- Application / Permit
- 23010-20000-03662
- Plan Check / Job No.
- B23VN12376
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN PROPOSED 7'-10" X 9'-6" 1-STORY ADDITION TO (E) SFD. CONVERT 21' X 21'-6" ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22 AND ADD 5'-6" X 9'-1" FOR FRONT PORCH. ADD 21' X 27'-4" 2ND FLOOR FOR NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/14/2024
- Issuing Office
- Current Status
- CofO Issued on 6/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2023 | RAPHAEL ROSAS |
| Corrections Issued | 9/27/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 10/3/2023 | STEVEN KIM |
| Applicant returned to address corrections | 4/25/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/7/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 5/13/2024 | RAPHAEL ROSAS |
| Issued | 5/14/2024 | APPLICANT |
| CofO in Progress | 5/5/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 6/9/2025 | JOHN JANSON |
| CofO Issued | 6/9/2025 | JOHN JANSON |
| Permit Finaled | 6/9/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2023 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 11/15/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 11/16/2023 | COLIN LOREDO |
| Miscellaneous | Cleared | 1/9/2024 | SPENCER WEJROWSKI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pineda,, Salvador Antonio; Lic. No.: S5233 | PO BOX 7313 ALHAMBRA, CA 91802 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/31/2024 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Rough | 5/31/2024 | Partial Approval | JEFFREY BULL |
| Sewer | 5/31/2024 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 6/28/2024 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 6/28/2024 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 7/2/2024 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 7/2/2024 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2024 | Partial Approval | JEFFREY BULL |
| BUILDING-Rough-Frame | 8/21/2024 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Rough | 8/21/2024 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 8/21/2024 | Not Ready for Inspection | JEFFREY BULL |
| HVAC-Rough | 8/21/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 9/18/2024 | Not Ready for Inspection | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Approved | JEFFREY BULL |
| Gas Test | 9/18/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 9/18/2024 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Rough | 9/18/2024 | Approved | JEFFREY BULL |
| Insulation | 9/24/2024 | Approved | SCOTT SOBEL |
| Interior/Exterior Lathing | 9/24/2024 | Not Ready for Inspection | SCOTT SOBEL |
| Interior/Exterior Lathing | 10/3/2024 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 10/7/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 10/7/2024 | Approved | JEFFREY BULL |
| Shower Pan | 10/7/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 10/10/2024 | Approved | JEFFREY BULL |
| Pre-Inspection | 4/1/2025 | Not Ready for Inspection | JUAN ALVARADO |
| BUILDING-Rough-Frame | 4/11/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 4/11/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Final | 4/11/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 4/11/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 4/11/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Final | 4/11/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 4/11/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 4/11/2025 | Approved | ARUTYUN MADATYAN |
| Shower Pan | 4/11/2025 | Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 4/11/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 4/17/2025 | Approved | ARUTYUN MADATYAN |
| Final | 4/17/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 4/17/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 4/17/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 5/5/2025 | Approved | ARUTYUN MADATYAN |
| Final | 5/5/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| Green Building Final | 5/5/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 5/5/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 5/5/2025 | Approved | ARUTYUN MADATYAN |