20410-20412 W DEVONSHIRE ST 91311
Certificate Information: 20410-20412 W DEVONSHIRE ST 91311
- Application / Permit
- 23010-20000-03657
- Plan Check / Job No.
- B23VN12348
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 41' X 21' DWELLING UNIT PER SB 9 ON FIRST FLOOR AND ACCESSORY DWELLING UNIT ON SECOND FLOOR; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 1/30/2024
- Issuing Office
- Current Status
- CofO Issued on 1/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2023 | SELLA BENYAMIN |
| Corrections Issued | 9/21/2023 | SELLA BENYAMIN |
| Quality Review Completed | 9/22/2023 | STEVEN KIM |
| Applicant returned to address corrections | 1/18/2024 | SELLA BENYAMIN |
| Plan Check Approved | 1/30/2024 | SELLA BENYAMIN |
| Issued | 1/30/2024 | APPLICANT |
| CofO in Progress | 1/14/2025 | DAVID SCANTLIN |
| Permit Finaled | 1/17/2025 | JOHN JANSON |
| CofO Issued | 1/17/2025 | JOHN JANSON |
| Permit Finaled | 1/17/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/18/2023 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 11/7/2023 | BRYAN GODINEZ |
| Low Impact Development (LID) | Cleared | 11/15/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 11/15/2023 | BRYAN GODINEZ |
| Senate Bill 9 | Cleared | 11/20/2023 | SPENCER WEJROWSKI |
| Hydrant and Access approval | Cleared | 1/5/2024 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/20/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| PLUMBING-Rough | 2/22/2024 | Partial Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 2/28/2024 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2024 | Partial Approval | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2024 | Approved | DAVID SCANTLIN |
| Green Building Rough | 3/22/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Interior/Exterior Lathing | 3/22/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 3/22/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Interior/Exterior Lathing | 4/11/2024 | Partial Approval | DAVID SCANTLIN |
| ELECTRICAL-Rough | 4/23/2024 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 4/23/2024 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 4/23/2024 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 5/17/2024 | Approved | DAVID SCANTLIN |
| Green Building Rough | 5/17/2024 | Approved | DAVID SCANTLIN |
| Insulation | 5/17/2024 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 5/17/2024 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 5/22/2024 | Corrections Issued | HENRY KIM |
| Drywall Nailing | 5/28/2024 | Approved | DAVID SCANTLIN |
| Shower Pan | 6/12/2024 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 7/5/2024 | Approved | JEFFREY PARD |
| Final | 9/3/2024 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 9/3/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 9/3/2024 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 9/3/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 9/3/2024 | Approved | DAVID SCANTLIN |
| Final | 1/14/2025 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 1/14/2025 | Approved | DAVID SCANTLIN |
| Service/Power Release | 1/14/2025 | Approved | DAVID SCANTLIN |