11031 N EL DORADO AVE 91331
Certificate Information: 11031 N EL DORADO AVE 91331
- Application / Permit
- 23010-20000-03629
- Plan Check / Job No.
- B23VN12249
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New 2-story Accessory Dwelling Unit (45' x 15'-2") per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 3/8/2024
- Issuing Office
- Current Status
- Issued on 3/8/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | VAHAN JIVALAGIAN |
| Corrections Issued | 10/5/2023 | VAHAN JIVALAGIAN |
| Quality Review Completed | 10/6/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 2/8/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 2/9/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 2/9/2024 | VAHAN JIVALAGIAN |
| Issued | 3/8/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/13/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 10/25/2023 | COLIN LOREDO |
| Clean Up Green Up | Cleared | 12/1/2023 | ALEX VELA |
| Low Impact Development (LID) | Cleared | 12/7/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 12/7/2023 | COLIN LOREDO |
| Construction near power lines | Cleared | 1/31/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Markarian Setrag; Lic. No.: 832632-B | , |
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | , |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| METHANE-Barrier | 6/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| METHANE-Subgrade | 6/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 6/20/2024 | No Access for Inspection | MICHEL ABAJAN |
| METHANE-Barrier | 6/20/2024 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 6/20/2024 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/24/2024 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/15/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 7/15/2024 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 7/23/2024 | Partial Approval | MICHEL ABAJAN |
| Deputy Wood Construction | 8/29/2024 | Conditional Approval | ROBERT GOLD |
| Rough-Elec/Plmb/HVAC | 9/6/2024 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/11/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 9/11/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 9/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Rough | 9/11/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| METHANE-Rough | 9/11/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 9/11/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/17/2024 | Corrections Issued | MICHEL ABAJAN |
| Green Building Rough | 9/17/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 9/17/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 9/17/2024 | Approved | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 9/17/2024 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 9/17/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/25/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 9/25/2024 | Approved | MICHEL ABAJAN |
| Insulation | 9/26/2024 | Corrections Issued | LOUIS ESCOTO |
| Drywall Nailing | 1/21/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 1/21/2025 | Approved | MICHEL ABAJAN |
| Final | 1/21/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 1/21/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 1/21/2025 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 1/21/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 1/21/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/21/2025 | SGSOV Not Required | MICHEL ABAJAN |
| Service/Power Release | 1/21/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 1/21/2025 | Approved | MICHEL ABAJAN |