11031 N EL DORADO AVE 91331

Certificate Information: 11031 N EL DORADO AVE 91331

Application / Permit
23010-20000-03629
Plan Check / Job No.
B23VN12249
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New 2-story Accessory Dwelling Unit (45' x 15'-2") per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 3/8/2024
Issuing Office
Current Status
Issued on 3/8/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/19/2023 APPLICANT
Assigned to Plan Check Engineer 9/28/2023 VAHAN JIVALAGIAN
Corrections Issued 10/5/2023 VAHAN JIVALAGIAN
Quality Review Completed 10/6/2023 OMID HEDAYAT
Applicant returned to address corrections 2/8/2024 VAHAN JIVALAGIAN
Applicant returned to address corrections 2/9/2024 VAHAN JIVALAGIAN
Plan Check Approved 2/9/2024 VAHAN JIVALAGIAN
Issued 3/8/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/13/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/25/2023 COLIN LOREDO
Sewer availability Cleared 10/25/2023 COLIN LOREDO
Clean Up Green Up Cleared 12/1/2023 ALEX VELA
Low Impact Development (LID) Cleared 12/7/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 12/7/2023 COLIN LOREDO
Construction near power lines Cleared 1/31/2024 RIDWAN HARDY

Contact Information

Contractor Markarian Setrag; Lic. No.: 832632-B       ,
Contractor Pampa Investment Inc; Lic. No.: 832632-B       ,
Engineer Moser,, Bradley Charles; Lic. No.: C68803 116 OAKSIDE LN      BUELLTON, CA 93427

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/17/2024 Not Ready for Inspection GREGG CUMMINGS
METHANE-Barrier 6/17/2024 Not Ready for Inspection GREGG CUMMINGS
METHANE-Subgrade 6/17/2024 Not Ready for Inspection GREGG CUMMINGS
Footing/Foundation/Slab 6/20/2024 No Access for Inspection MICHEL ABAJAN
METHANE-Barrier 6/20/2024 Approved MICHEL ABAJAN
METHANE-Subgrade 6/20/2024 Approved MICHEL ABAJAN
Footing/Foundation/Slab 6/24/2024 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 7/15/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 7/15/2024 Partial Approval MICHEL ABAJAN
Wood Frame 7/23/2024 Partial Approval MICHEL ABAJAN
Deputy Wood Construction 8/29/2024 Conditional Approval ROBERT GOLD
Rough-Elec/Plmb/HVAC 9/6/2024 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 9/11/2024 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 9/11/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 9/11/2024 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 9/11/2024 Corrections Issued JENNIFER RABUCHIN
MERV13>=Rough 9/11/2024 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Rough 9/11/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 9/11/2024 Corrections Issued JENNIFER RABUCHIN
Verify Sprinkler Sign Off 9/11/2024 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/17/2024 Corrections Issued MICHEL ABAJAN
Green Building Rough 9/17/2024 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 9/17/2024 Approved MICHEL ABAJAN
MERV13>=Rough 9/17/2024 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 9/17/2024 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 9/17/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 9/25/2024 Approved MICHEL ABAJAN
Green Building Rough 9/25/2024 Approved MICHEL ABAJAN
Insulation 9/26/2024 Corrections Issued LOUIS ESCOTO
Drywall Nailing 1/21/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 1/21/2025 Approved MICHEL ABAJAN
Final 1/21/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 1/21/2025 Approved MICHEL ABAJAN
HVAC-Final 1/21/2025 Approved MICHEL ABAJAN
MERV13>=Final 1/21/2025 Approved MICHEL ABAJAN
PLUMBING-Final 1/21/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/21/2025 SGSOV Not Required MICHEL ABAJAN
Service/Power Release 1/21/2025 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 1/21/2025 Approved MICHEL ABAJAN