21710 W VICTORY BLVD 91367

Certificate Information: 21710 W VICTORY BLVD 91367

Application / Permit
23010-20000-03627
Plan Check / Job No.
B23VN12239
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(9) Gas Station
Work Description
EPLAN ENLARGE EXISTING GAS STATION WITH CANOPY.
Permit Issued
Issued on 7/23/2024
Issuing Office
Current Status
CofO Issued on 5/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 RAPHAEL ROSAS
Corrections Issued 9/25/2023 RAPHAEL ROSAS
Quality Review Completed 9/28/2023 STEVEN KIM
Applicant returned to address corrections 5/7/2024 RAPHAEL ROSAS
Plan Check Approved 7/23/2024 RAPHAEL ROSAS
Issued 7/23/2024 APPLICANT
TCO Issued (Expire Date: 04-14-2025) 10/16/2024 JEFFREY DURAN
CofO in Progress 4/30/2025 BRIAN KELLY
Permit Finaled 5/2/2025 JEFFREY DURAN
CofO Issued 5/2/2025 JEFFREY DURAN
Permit Finaled 5/2/2025 JEFFREY DURAN

Permit Application Clearance Information

Green Code Cleared 9/12/2023 MICHAEL AYERS
DAS Clearance Cleared 9/27/2023 Hernan Arreola
Frnt yard landscape/Water mgmt Cleared 10/2/2023 ALEX VELA
Miscellaneous Cleared 10/2/2023 ALEX VELA
Miscellaneous Cleared 10/2/2023 ALEX VELA
Miscellaneous Cleared 10/2/2023 ALEX VELA
Miscellaneous Cleared 10/2/2023 ALEX VELA
Miscellaneous Cleared 10/2/2023 ALEX VELA
Miscellaneous Cleared 10/2/2023 ALEX VELA
Miscellaneous Cleared 10/2/2023 ALEX VELA
Miscellaneous Cleared 10/2/2023 ALEX VELA
Miscellaneous Cleared 10/2/2023 ALEX VELA
ZA Case Cleared 10/2/2023 ALEX VELA
Tract Map conditions Cleared 10/4/2023 ALEX VELA
Tract Map conditions Cleared 10/4/2023 ALEX VELA
Tract Map conditions Cleared 10/4/2023 ALEX VELA
Tract Map conditions Cleared 10/4/2023 ALEX VELA
Tract Map conditions Cleared 10/4/2023 ALEX VELA
Prkng lot landscape/Water mgmt Cleared 10/6/2023 ALEX VELA
Address approval Cleared 10/12/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/12/2023 COLIN LOREDO
Work Adjacent to Public Way Cleared 10/17/2023 COLIN LOREDO
Hydrant and Access approval Cleared 10/28/2023 KURT CORRAL
Hydrant and Access approval Cleared 10/28/2023 KURT CORRAL
Low Impact Development (LID) Cleared 3/26/2024 ANDRES COVARRUBIAS
Highway dedication Cleared 5/1/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/1/2024 CARLOS AGUILERA
Food Service Establishment Cleared 5/13/2024 CRYSTOL BRANDT
Internal circulation Cleared 5/30/2024 SHEILA AHORAIAN
Specific Plan Cleared 5/30/2024 SHEILA AHORAIAN
Specific Plan Cleared 6/3/2024 SHEILA GERSHON

Contact Information

Architect Odle,, Terry Wynn; Lic. No.: C21913 3487 CASTLERIDGE DR      TUCKER, GA 30084
Contractor Jones/Covey Group Incorporated; Lic. No.: 804431-B       ,
Engineer Crystal,, Brian Elliott; Lic. No.: GE2639 19526 STARFISH LN      HUNTINGTON BEACH, CA 92648
Engineer Mele,, Gerald; Lic. No.: S2663 7337 N FIRST ST   SUITE 110    FRESNO, CA 93710

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/26/2024 Not Ready for Inspection BRIAN KELLY
Excavation/Setback/Form/Re-Bar 7/30/2024 Partial Inspection BRIAN KELLY
Piling/Pier/Caisson 8/2/2024 Not Ready for Inspection BRIAN KELLY
Footing/Foundation/Slab 8/5/2024 Not Ready for Inspection BRIAN KELLY
Excavation/Setback/Form/Re-Bar 8/6/2024 Not Ready for Inspection BRIAN KELLY
Deputy Reinf. Concrete 8/8/2024 Conditional Approval BRIAN KELLY
Footing/Foundation/Slab 8/8/2024 Partial Inspection DEANDRE HOFFMAN
Piling/Pier/Caisson 8/9/2024 Partial Inspection DEANDRE HOFFMAN
Deputy Reinf. Concrete 8/12/2024 Conditional Approval BRIAN KELLY
Deputy Steel/Welding 8/27/2024 Conditional Approval BRIAN KELLY
Deputy Reinf. Concrete 8/28/2024 Conditional Approval BRIAN KELLY
Deputy Steel/Welding 9/5/2024 Conditional Approval BRIAN KELLY
Deputy Steel/Welding 9/10/2024 Conditional Approval BRIAN KELLY
Footing/Foundation/Slab 9/11/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 9/12/2024 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 9/12/2024 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 9/13/2024 Conditional Approval BRIAN KELLY
Structural Steel Frame 9/13/2024 Not Ready for Inspection BRIAN KELLY
Footing/Foundation/Slab 9/17/2024 Partial Approval DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 9/18/2024 Partial Approval BRIAN KELLY
Deputy Reinf. Concrete 9/19/2024 Conditional Approval BRIAN KELLY
Deputy Steel/Welding 9/19/2024 Conditional Approval BRIAN KELLY
Footing/Foundation/Slab 9/19/2024 Partial Inspection BRIAN KELLY
Deputy Reinf. Concrete 9/20/2024 Conditional Approval BRIAN KELLY
Footing/Foundation/Slab 9/20/2024 Partial Approval BRIAN KELLY
Excavation/Setback/Form/Re-Bar 9/24/2024 Not Ready for Inspection BRIAN KELLY
Deputy Reinf. Concrete 9/25/2024 Conditional Approval BRIAN KELLY
Excavation/Setback/Form/Re-Bar 9/25/2024 Partial Approval BRIAN KELLY
Footing/Foundation/Slab 9/25/2024 Partial Approval BRIAN KELLY
Deputy Reinf. Concrete 9/26/2024 Conditional Approval BRIAN KELLY
Deputy Reinf. Concrete 10/1/2024 Conditional Approval BRIAN KELLY
Final 10/11/2024 OK for TCO ROBERT DAVIS
Footing/Foundation/Slab 10/11/2024 Approved ROBERT DAVIS
Green Building Final 10/11/2024 Approved ROBERT DAVIS
Green Building Rough 10/11/2024 Approved ROBERT DAVIS
Reinforced Masonry Frame 10/11/2024 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 10/11/2024 SGSOV No Gas ROBERT DAVIS
Smoke Detectors 10/11/2024 Approved ROBERT DAVIS
Special/Order Compliance 3/18/2025 Partial Inspection BRIAN KELLY
Final 4/30/2025 OK to Issue CofO BRIAN KELLY