695-695 1/4 E 43RD ST 90011
Certificate Information: 695-695 1/4 E 43RD ST 90011
- Application / Permit
- 23010-20000-03626
- Plan Check / Job No.
- B23VN12224
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c)(d) W/ SFD ABOVE (NFPA-13D FIRE SPRINKLERS THROUGHOUT) ** ePlan**
- Permit Issued
- Issued on 4/11/2024
- Issuing Office
- Current Status
- CofO Issued on 1/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 9/28/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 9/28/2023 | STEVEN KIM |
| Applicant returned to address corrections | 1/4/2024 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 1/31/2024 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 2/1/2024 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 4/5/2024 | NILOOFAR MEHRAIN |
| Plan Check Approved | 4/10/2024 | NILOOFAR MEHRAIN |
| Issued | 4/11/2024 | APPLICANT |
| CofO in Progress | 1/23/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 1/26/2025 | DEROLD HAUFF |
| CofO Issued | 1/26/2025 | DEROLD HAUFF |
| Permit Finaled | 1/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/18/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2023 | WALLIE JONG |
| Sewer availability | Cleared | 10/25/2023 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 12/1/2023 | LAVEON RIDER |
| Low Impact Development (LID) | Cleared | 3/18/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 3/20/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nosrat,, Mehrdad Michael; Lic. No.: C77203 | PO BOX 5154 DIAMOND BAR, CA 91765 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/21/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 5/21/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 5/23/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 7/2/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/2/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 7/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 7/15/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/15/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/15/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/17/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 7/17/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/17/2024 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 7/17/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 7/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 7/26/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 7/26/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 7/31/2024 | Approved | ALEX COLIN |
| Shower Pan | 7/31/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 8/6/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 8/16/2024 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 11/15/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 11/15/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 11/15/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/15/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 11/15/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 11/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 11/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 11/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 11/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/27/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/27/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/27/2024 | Partial Approval | MICHAEL LEWIS |
| Final | 1/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/22/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 1/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/22/2025 | Approved | ALEJANDRO DE ARTOLA |