932 1/4-1/2 E 42ND PL 90011
Certificate Information: 932 1/4-1/2 E 42ND PL 90011
- Application / Permit
- 23010-20000-03604
- Plan Check / Job No.
- B23VN12185
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 24'-6" X 32'-0" STRUCTURE CONSISTING OF TWO 24'-6" X 16'-0" ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g) - PER ENGINEER **NFPA-13D FIRE SPRINKLERED THROUGHOUT
- Permit Issued
- Issued on 1/19/2024
- Issuing Office
- Current Status
- Issued on 1/19/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 9/18/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 11/27/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 12/11/2023 | DANIEL ABRAMYAN |
| Issued | 1/19/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/5/2023 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2023 | DAVID LOPEZ |
| Sewer availability | Cleared | 10/12/2023 | DAVID LOPEZ |
| Low Impact Development (LID) | Cleared | 11/21/2023 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 11/21/2023 | JUSTIN BICOL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 3/6/2024 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 3/19/2024 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 7/17/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/17/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/17/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 7/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 7/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 7/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/6/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/6/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/6/2024 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 8/6/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 8/16/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 8/16/2024 | Partial Approval | ALEX COLIN |
| Drywall Nailing | 9/12/2024 | Approved | ALEJANDRO DE ARTOLA |
| Shower Pan | 10/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 2/3/2025 | Corrections Issued | JOSH MEISTER |
| Sewer | 2/19/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/3/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/3/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/3/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/3/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/18/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/18/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/18/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/18/2026 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/18/2026 | Approved | ALEJANDRO DE ARTOLA |