1040-1042 W 60TH ST 90044

Certificate Information: 1040-1042 W 60TH ST 90044

Application / Permit
23010-20000-03573
Plan Check / Job No.
B23VN12092
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSE TWO STORY DUPLEX WITH ATTACHED 3 CAR GARAGE AND 1 OPEN PARKING _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 1/19/2024
Issuing Office
Current Status
CofO Issued on 8/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 DAWN MC NULTY
Corrections Issued 9/26/2023 DAWN MC NULTY
Quality Review Completed 9/28/2023 STEVEN KIM
Applicant returned to address corrections 12/14/2023 DAWN MC NULTY
Applicant returned to address corrections 12/19/2023 DAWN MC NULTY
Applicant returned to address corrections 12/26/2023 DAWN MC NULTY
Plan Check Approved 12/27/2023 DAWN MC NULTY
Issued 1/19/2024 APPLICANT
CofO in Progress 7/23/2024 JOSE MACIAS
CofO Issued 8/5/2024 DEROLD HAUFF
Permit Finaled 8/5/2024 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 10/12/2023 RYAN LY
Address approval Cleared 10/14/2023 CELINA MORENO
Highway dedication Cleared 10/14/2023 CELINA MORENO
Permit Cleared 10/14/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 10/17/2023 CELINA MORENO
Sewer availability Cleared 10/24/2023 CELINA MORENO
Low Impact Development (LID) Cleared 10/27/2023 MELINEH AGHAKHABIAN
Hydrant and Access approval Cleared 10/28/2023 KURT CORRAL
Roof/Waste drainage to street Cleared 11/3/2023 CELINA MORENO
SB8 RUD Cleared 11/15/2023 CHARLOTTE KINGS
Trees in Parkway Cleared 12/5/2023 ADALBERTO VERA

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B       ,
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/13/2024 Approved RONNIE MINDANAO
Footing/Foundation/Slab 2/13/2024 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Not Ready for Inspection ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/11/2024 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 3/11/2024 Approved ALEJANDRO DE ARTOLA
Wood Frame 3/11/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Partial Approval ALEJANDRO DE ARTOLA
Insulation 3/12/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/28/2024 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 4/18/2024 Approved CRAIG DAVIS
HVAC-Rough 4/29/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 4/29/2024 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 4/30/2024 Approved JOSE MACIAS
ELECTRICAL-Rough 4/30/2024 Approved JOSE MACIAS
HVAC-Rough 4/30/2024 Approved JOSE MACIAS
PLUMBING-Rough 4/30/2024 Approved JOSE MACIAS
Verify Sprinkler Sign Off 4/30/2024 Approved JOSE MACIAS
Insulation 5/1/2024 Approved CRAIG DAVIS
Drywall Nailing 5/14/2024 Approved CRAIG DAVIS
Interior/Exterior Lathing 5/14/2024 Approved CRAIG DAVIS
ELECTRICAL-Final 6/21/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Final 7/11/2024 Corrections Issued CRAIG DAVIS
Final 7/11/2024 Not Ready for Inspection CRAIG DAVIS
HVAC-Final 7/11/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Final 7/11/2024 Corrections Issued CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 7/11/2024 SGSOV Not Ready CRAIG DAVIS
Service/Power Release 7/11/2024 Not Ready for Inspection CRAIG DAVIS
Smoke Detectors 7/11/2024 Approved CRAIG DAVIS
ELECTRICAL-Final 7/22/2024 Approved JOSE MACIAS
Final 7/22/2024 OK to Issue CofO JOSE MACIAS
HVAC-Final 7/22/2024 Approved JOSE MACIAS
PLUMBING-Final 7/22/2024 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 7/22/2024 SGSOV Not Required JOSE MACIAS
Service/Power Release 7/22/2024 Approved JOSE MACIAS