6864-6866 N TYRONE AVE 91405

Certificate Information: 6864-6866 N TYRONE AVE 91405

Application / Permit
23010-20000-03553
Plan Check / Job No.
B23VN11996
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 42' X 20' 2-STORY (2) ACCESSORY DWELLING UNITS AS PER CA GOVT CODE 65852.2(E)(1)(D), NFPA-13D FIRE SPRINKLERS REQUIRED THOUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/6/2024
Issuing Office
Current Status
CofO Issued on 5/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/5/2023 APPLICANT
Assigned to Plan Check Engineer 9/7/2023 RARES BODEA
Corrections Issued 9/13/2023 RARES BODEA
Quality Review Completed 9/14/2023 STEVEN KIM
Building Plans Picked Up 9/14/2023 APPLICANT
Plan Check Approved 6/6/2024 RARES BODEA
Issued 6/6/2024 APPLICANT
CofO in Progress 4/28/2025 RYAN SALAZAR
Permit Finaled 5/6/2025 RUBEN SALAS
CofO Issued 5/6/2025 RUBEN SALAS
Permit Finaled 5/6/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/21/2023 MEGAN GODINEZ
Sewer availability Cleared 9/26/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/30/2023 NIKKI ZULUETA
Low Impact Development (LID) Cleared 10/13/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 10/31/2023 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/1/2024 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 7/8/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 8/20/2024 Approved RYAN SALAZAR
PLUMBING-Rough 9/20/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/9/2024 Partial Approval RYAN SALAZAR
Insulation 10/29/2024 Approved RYAN SALAZAR
Drywall Nailing 11/14/2024 Approved RYAN SALAZAR
Green Building Rough 11/14/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/4/2024 Approved RYAN SALAZAR
Shower Pan 12/4/2024 Approved RYAN SALAZAR
Underground Mechanical 12/18/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 4/21/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 4/21/2025 Approved RYAN SALAZAR
Final 4/21/2025 OK to Issue CofO RYAN SALAZAR
Green Building Final 4/21/2025 Approved RYAN SALAZAR
HVAC-Final 4/21/2025 Approved RYAN SALAZAR
HVAC-Rough 4/21/2025 Approved RYAN SALAZAR
PLUMBING-Final 4/21/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/21/2025 SGSOV Not Required RYAN SALAZAR
Service/Power Release 4/21/2025 Approved RYAN SALAZAR
Smoke Detectors 4/21/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 4/21/2025 Approved RYAN SALAZAR