6476 N MARY ELLEN AVE 91401
Certificate Information: 6476 N MARY ELLEN AVE 91401
- Application / Permit
- 23010-20000-03513
- Plan Check / Job No.
- B23VN11832
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. New 30' X 20' Detached 2-Story Accessory Dwelling Unit as per Lamc 12.22.A33(c) and (d), all work per engineering
- Permit Issued
- Issued on 12/5/2023
- Issuing Office
- Current Status
- CofO Issued on 1/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2023 | RARES BODEA |
| Corrections Issued | 9/18/2023 | RARES BODEA |
| Quality Review Completed | 9/18/2023 | STEVEN KIM |
| Applicant returned to address corrections | 11/29/2023 | RARES BODEA |
| Plan Check Approved | 11/30/2023 | RARES BODEA |
| Issued | 12/5/2023 | APPLICANT |
| CofO in Progress | 12/3/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 1/17/2025 | RUBEN SALAS |
| CofO Issued | 1/17/2025 | RUBEN SALAS |
| Permit Finaled | 1/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/25/2023 | RIDWAN HARDY |
| Address approval | Cleared | 9/27/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 9/27/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 9/27/2023 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 10/24/2023 | BRYAN GODINEZ |
| Low Impact Development (LID) | Cleared | 10/27/2023 | ROGELIO CORTES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gosen,, James; Lic. No.: C43590 | 15315 BLEDSOE ST SYLMAR, CA 91342 |
| Engineer | Gosen,, James; Lic. No.: NA43590 | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/15/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 1/10/2024 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 1/16/2024 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 2/9/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2024 | Partial Approval | KIRK SANDERS |
| Wood Frame | 2/16/2024 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 2/26/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 3/19/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 3/19/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 3/22/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 3/28/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 3/28/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/4/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 4/4/2024 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 4/4/2024 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 4/26/2024 | Approved | JOSE AVILA |
| Green Building Rough | 4/26/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 4/26/2024 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 4/26/2024 | Approved | JOSE AVILA |
| Deputy Drilled-In Anchors | 4/29/2024 | Conditional Approval | JUAN VALENZUELA |
| Insulation | 4/30/2024 | Approved | JOSE AVILA |
| Drywall Nailing | 5/6/2024 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 6/17/2024 | Approved | MATTHEW NELSON |
| HVAC-Final | 6/17/2024 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Final | 6/17/2024 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Final | 9/30/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 9/30/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 9/30/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 9/30/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/30/2024 | SGSOV Not Required | OGANES TARAKHCHYAN |
| Service/Power Release | 9/30/2024 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 9/30/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 10/2/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |