12506 W CORRENTI ST 91331
Certificate Information: 12506 W CORRENTI ST 91331
- Application / Permit
- 23010-20000-03505
- Plan Check / Job No.
- B23VN11786
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 30'-0" X 40'-0" DETACHED FULLY ELECTRIC ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 4/24/2024
- Issuing Office
- Current Status
- CofO Issued on 7/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 9/8/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 3/8/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 3/30/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 4/9/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 4/17/2024 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 4/24/2024 | GIOVANNY CHAVEZ |
| Issued | 4/24/2024 | APPLICANT |
| CofO in Progress | 7/16/2025 | MICHEL ABAJAN |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
| CofO Issued | 7/31/2025 | RUBEN SALAS |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 10/10/2023 | COLIN LOREDO |
| ZI | Cleared | 12/4/2023 | NATHAN ROMINE |
| Low Impact Development (LID) | Cleared | 2/26/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 3/2/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hakhamaneshi,, Manouchehr; Lic. No.: C88083 | 12935 ALCOSTA BLVD PO BOX 1435 SAN RAMON, CA 94583 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/9/2024 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 6/6/2024 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/14/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2024 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 8/7/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/20/2024 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/20/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 8/20/2024 | Approved | DAVID ANDERSON |
| HVAC-Rough | 8/20/2024 | Approved | DAVID ANDERSON |
| Deputy Wood Construction | 8/23/2024 | Conditional Approval | DAVID MATSON |
| Insulation | 8/28/2024 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 8/28/2024 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 9/11/2024 | Approved | MATTHEW NELSON |
| Shower Pan | 9/25/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/1/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/3/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 4/3/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/3/2025 | Approved | MICHEL ABAJAN |
| Final | 7/15/2025 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 7/15/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/15/2025 | SGSOV Not Required | MICHEL ABAJAN |
| Service/Power Release | 7/15/2025 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 7/15/2025 | Approved | MICHEL ABAJAN |