7933 N STANSBURY AVE 91402

Certificate Information: 7933 N STANSBURY AVE 91402

Application / Permit
23010-20000-03481
Plan Check / Job No.
B23VN11673
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) DETACHED 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d).
Permit Issued
Issued on 11/25/2023
Issuing Office
Current Status
CofO Issued on 8/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2023 APPLICANT
Assigned to Plan Check Engineer 9/8/2023 MADISON ODELL
Corrections Issued 9/9/2023 MADISON ODELL
Applicant returned to address corrections 10/11/2023 MADISON ODELL
Applicant returned to address corrections 10/17/2023 MICHAEL LOPEZ
Plan Check Approved 11/13/2023 HERNAN ARREOLA
Issued 11/25/2023 APPLICANT
CofO in Progress 7/24/2024 GREGG CUMMINGS
Permit Finaled 8/6/2024 RUBEN SALAS
CofO Issued 8/6/2024 RUBEN SALAS
Permit Finaled 8/6/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/10/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 10/16/2023 NIKKI ZULUETA
Sewer availability Cleared 10/16/2023 NIKKI ZULUETA
Low Impact Development (LID) Cleared 11/3/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 11/3/2023 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Matevosyan,, Nzhde; Lic. No.: C92008 10853 NASSAU AVE      SUNLAND, CA 91040

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/12/2023 Approved GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 12/28/2023 Not Ready for Inspection JOHN COLEMAN
PLUMBING-Rough 12/28/2023 Partial Approval JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 1/5/2024 Approved JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Partial Approval GREGG CUMMINGS
Green Building Rough 1/18/2024 Not Ready for Inspection GREGG CUMMINGS
Verify Sprinkler Sign Off 1/18/2024 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 2/7/2024 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 2/7/2024 Not Ready for Inspection GREGG CUMMINGS
Green Building Rough 2/7/2024 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 2/7/2024 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 2/7/2024 Approved GREGG CUMMINGS
Verify Sprinkler Sign Off 2/7/2024 Approved GREGG CUMMINGS
Wood Frame 2/7/2024 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 2/27/2024 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 2/27/2024 Approved GREGG CUMMINGS
ELECTRICAL-Rough 3/1/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 3/1/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 3/1/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/5/2024 Approved GREGG CUMMINGS
Green Building Rough 3/5/2024 Approved GREGG CUMMINGS
Insulation 3/11/2024 Approved MATTHEW NELSON
Drywall Nailing 3/14/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 3/27/2024 Partial Approval GREGG CUMMINGS
Final 5/17/2024 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 5/17/2024 Approved VINCENT HANLEY
Green Building Final 5/17/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/17/2024 SGSOV Not Required VINCENT HANLEY
Service/Power Release 5/17/2024 Approved VINCENT HANLEY
Smoke Detectors 5/17/2024 Approved VINCENT HANLEY
ELECTRICAL-Final 7/23/2024 Approved GREGG CUMMINGS
Final 7/23/2024 OK to Issue CofO GREGG CUMMINGS