16523 W DEVONSHIRE ST 91344

Certificate Information: 16523 W DEVONSHIRE ST 91344

Application / Permit
23010-20000-03480
Plan Check / Job No.
B23VN11672
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) DETACHED 2-STORY ACCESSORY DWELLING UNIT W/ ATTACHED 2-CAR GARAGE PER LAMC 12.22A33(c)(d) **ePlan **
Permit Issued
Issued on 8/13/2024
Issuing Office
Current Status
Issued on 8/13/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/31/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 NILOOFAR MEHRAIN
Corrections Issued 9/18/2023 NILOOFAR MEHRAIN
Quality Review Completed 9/22/2023 STEVEN KIM
Applicant returned to address corrections 4/24/2024 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/24/2024 NILOOFAR MEHRAIN
Applicant returned to address corrections 7/16/2024 NILOOFAR MEHRAIN
Plan Check Approved 7/18/2024 NILOOFAR MEHRAIN
Issued 8/13/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/19/2023 COLIN LOREDO
Hydrant and Access approval Cleared 11/22/2023 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 11/29/2023 COLIN LOREDO
Sewer availability Cleared 11/29/2023 COLIN LOREDO
Low Impact Development (LID) Cleared 3/8/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 3/11/2024 MARKOS PEREZ-BRAN
Permit Cleared 3/19/2024 LEE GUILBEAUX
Trees in Parkway Cleared 4/4/2024 ADALBERTO VERA

Contact Information

Contractor Owner-Builder       ,
Engineer Mobed,, Ashkan; Lic. No.: C92493 23450 KITTREDGE ST      WEST HILLS, CA 91307

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/11/2025 Approved NICHOLAS TROWBRIDGE
Pre-Inspection 12/3/2025 Approved CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 12/22/2025 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 12/22/2025 Partial Approval CHRISTOPHER ROJAS
Sewer 12/22/2025 Approved CHRISTOPHER ROJAS
Special/Order Compliance 12/22/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 4/15/2026 Corrections Issued KEVIN BERBERYAN
Special/Order Compliance 4/15/2026 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 4/20/2026 Partial Approval JOSE AVILA