741 E 97TH ST 90002
Certificate Information: 741 E 97TH ST 90002
- Application / Permit
- 23010-20000-03458
- Plan Check / Job No.
- B23VN11599
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 26'-5" X 18'-2" DETACHED ACCESSORY DWELLING PER LAMC 12.22 A.33(c) and (d) - PER ENGINEER
- Permit Issued
- Issued on 4/16/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 9/2/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 9/8/2023 | APPLICANT |
| Plan Check Approved | 2/23/2024 | DANIEL ABRAMYAN |
| Issued | 4/16/2024 | APPLICANT |
| CofO in Progress | 9/24/2024 | BEN MOLSTAD |
| CofO Issued | 9/24/2024 | ANSON MAGLASANG |
| Permit Finaled | 9/24/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 10/6/2023 | DAVID LOPEZ |
| Low Impact Development (LID) | Cleared | 2/2/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 3/20/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/10/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 4/10/2024 | DAVID LOPEZ |
Contact Information
| Contractor | Sarahang Construction Inc; Lic. No.: 897724-B | 39312 DUNBAR PALMDALE, CA 93551 |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 22634 SYLVAN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/23/2024 | Partial Approval | BEN MOLSTAD |
| Footing/Foundation/Slab | 4/30/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 5/29/2024 | Corrections Issued | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2024 | Approved | BEN MOLSTAD |
| Gas Test | 5/29/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 5/29/2024 | Corrections Issued | BEN MOLSTAD |
| Sewer | 5/29/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Wood Frame | 5/29/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 6/5/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 6/5/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 6/5/2024 | Approved | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 6/5/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Wood Frame | 6/5/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 6/10/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 6/20/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 9/3/2024 | Not Ready for Inspection | BARRY HACHE |
| Final | 9/3/2024 | Corrections Issued | BARRY HACHE |
| Green Building Final | 9/3/2024 | Not Ready for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 9/3/2024 | SGSOV Not Ready | BARRY HACHE |
| Service/Power Release | 9/3/2024 | Not Ready for Inspection | BARRY HACHE |
| Smoke Detectors | 9/3/2024 | Not Ready for Inspection | BARRY HACHE |
| Verify Sprinkler Sign Off | 9/3/2024 | Not Ready for Inspection | BARRY HACHE |
| Special/Order Compliance | 9/6/2024 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 9/17/2024 | Approved | BARRY HACHE |
| Final | 9/17/2024 | Not Ready for Inspection | BARRY HACHE |
| Green Building Final | 9/17/2024 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 9/17/2024 | SGSOV Approved | BARRY HACHE |
| Service/Power Release | 9/17/2024 | Corrections Issued | BARRY HACHE |
| Smoke Detectors | 9/17/2024 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 9/17/2024 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 9/23/2024 | Approved | BEN MOLSTAD |
| Final | 9/23/2024 | OK to Issue CofO | BEN MOLSTAD |
| Green Building Final | 9/23/2024 | Approved | BEN MOLSTAD |
| HVAC-Final | 9/23/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 9/23/2024 | Approved | BEN MOLSTAD |
| Service/Power Release | 9/23/2024 | Approved | BEN MOLSTAD |