7747 W VALMONT ST 91042
Certificate Information: 7747 W VALMONT ST 91042
- Application / Permit
- 23010-20000-03434
- Plan Check / Job No.
- B23VN11550
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 32'-0" X 26'-7" DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 9/26/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 9/2/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 9/6/2023 | APPLICANT |
| Plan Check Approved | 9/21/2023 | ALEC MOUSAKHANIAN |
| Issued | 9/26/2023 | APPLICANT |
| CofO in Progress | 8/31/2024 | DAVID ANDERSON |
| Permit Finaled | 9/17/2024 | DANIEL ORRANTE |
| CofO Issued | 9/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/7/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2023 | TAL SHEMEN |
| Grading Pre-Inspection | Cleared | 9/11/2023 | ROBERT PINA |
| Sewer availability | Cleared | 9/11/2023 | TAL SHEMEN |
| Low Impact Development (LID) | Cleared | 9/19/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 9/20/2023 | TAL SHEMEN |
| GPI Written Notices | Cleared | 9/21/2023 | ALEC MOUSAKHANIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/17/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 10/30/2023 | Partial Approval | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 11/13/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 11/29/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 11/29/2023 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 12/11/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2023 | Partial Approval | DAVID ANDERSON |
| Green Building Rough | 12/11/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 12/11/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 12/11/2023 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 12/14/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 12/14/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 12/19/2023 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 12/21/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 12/21/2023 | Approved | DAVID ANDERSON |
| Insulation | 12/22/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Insulation | 12/27/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 1/5/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 1/5/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/12/2024 | Approved | DAVID ANDERSON |
| Gas Test | 3/15/2024 | Approved | MATTHEW NELSON |
| Sewer | 3/15/2024 | Corrections Issued | MATTHEW NELSON |
| Underground Mechanical | 3/15/2024 | Partial Approval | MATTHEW NELSON |
| Sewer | 3/19/2024 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 3/22/2024 | Corrections Issued | DAVID ANDERSON |
| Underground Mechanical | 3/22/2024 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 4/8/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 4/30/2024 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 4/30/2024 | Approved | DAVID ANDERSON |
| Green Building Final | 4/30/2024 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 4/30/2024 | SGSOV Not Required | DAVID ANDERSON |
| Service/Power Release | 4/30/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 4/30/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 7/5/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Final | 7/5/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Service/Power Release | 7/5/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 7/5/2024 | Approved | DAVID ANDERSON |
| Pre-Inspection | 7/9/2024 | Approved | DAVID ANDERSON |
| Final | 7/25/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Final | 7/25/2024 | Approved | DAVID ANDERSON |
| Service/Power Release | 7/25/2024 | Approved | DAVID ANDERSON |
| Final | 7/26/2024 | Corrections Issued | DAVID ANDERSON |
| Final | 8/26/2024 | OK to Issue CofO | DAVID ANDERSON |