4146 N ST CLAIR AVE 91604
Certificate Information: 4146 N ST CLAIR AVE 91604
- Application / Permit
- 23010-20000-03431
- Plan Check / Job No.
- B23VN11531
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 37'-10" x 70'-1 3/4" IRR. SHAPED 2-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE & ATT. OPEN TRELLIS; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 1/5/2024
- Issuing Office
- Current Status
- CofO Issued on 4/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2023 | SEAN SHAHMIRI |
| Corrections Issued | 9/5/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 9/6/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 9/11/2023 | APPLICANT |
| Applicant returned to address corrections | 12/21/2023 | SEAN SHAHMIRI |
| Plan Check Approved | 12/21/2023 | SEAN SHAHMIRI |
| No Progress | 12/21/2023 | SEAN SHAHMIRI |
| Plan Check Approved | 1/3/2024 | SEAN SHAHMIRI |
| Issued | 1/5/2024 | APPLICANT |
| CofO in Progress | 2/27/2025 | CHRISTOPHE COCHRAN |
| Permit Finaled | 4/1/2025 | RUBEN SALAS |
| CofO Issued | 4/1/2025 | RUBEN SALAS |
| Permit Finaled | 4/1/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/20/2023 | LAVEON RIDER |
| Address approval | Cleared | 11/7/2023 | COLIN LOREDO |
| Permit | Cleared | 11/7/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 11/8/2023 | COLIN LOREDO |
| ZI | Cleared | 11/14/2023 | SPENCER WEJROWSKI |
| Low Impact Development (LID) | Cleared | 11/27/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/30/2023 | EDGAR ALCARAZ |
| Trees in Parkway | Cleared | 12/11/2023 | ADALBERTO VERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/16/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Underground Mechanical | 2/16/2024 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 2/27/2024 | Approved | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 3/20/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 4/15/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 5/29/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Sewer | 5/29/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Sewer | 5/31/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 6/4/2024 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 6/5/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 6/24/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Rough | 6/24/2024 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 6/28/2024 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 7/10/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 7/19/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 7/19/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 7/19/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 7/31/2024 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 7/31/2024 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 7/31/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/7/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/9/2024 | Not Ready for Inspection | MICHAEL CORTEZ |
| Insulation | 8/13/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/13/2024 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 8/19/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/26/2024 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 8/28/2024 | Approved | CHRISTOPHE COCHRAN |
| Enclosure/Fence | 1/10/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Final | 1/10/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Enclosure/Fence | 1/27/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 1/27/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Not Required | CHRISTOPHE COCHRAN |
| Smoke Detectors | 1/27/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 2/25/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 2/25/2025 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 2/25/2025 | Approved | CHRISTOPHE COCHRAN |