14816 W ASTORIA ST 91342

Certificate Information: 14816 W ASTORIA ST 91342

Application / Permit
23010-20000-03400
Plan Check / Job No.
B23VN11387
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21'-6" X 31'-4" DETACHED 2-STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g) AT SOUTH SIDE OF LOT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/12/2024
Issuing Office
Current Status
CofO Issued on 6/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2023 APPLICANT
Assigned to Plan Check Engineer 8/31/2023 RAPHAEL ROSAS
Corrections Issued 9/7/2023 RAPHAEL ROSAS
Quality Review Completed 9/7/2023 STEVEN KIM
Building Plans Picked Up 9/8/2023 APPLICANT
Applicant returned to address corrections 2/20/2024 RAPHAEL ROSAS
Plan Check Approved 2/22/2024 RAPHAEL ROSAS
Issued 3/12/2024 APPLICANT
CofO in Progress 4/10/2026 JENNIFER RABUCHIN
Permit Finaled 6/4/2026 RUBEN SALAS
CofO Issued 6/4/2026 RUBEN SALAS
Permit Finaled 6/4/2026 RUBEN SALAS

Permit Application Clearance Information

Tract Map conditions Cleared 9/13/2023 STEVEN WECHSLER
ZA Case Cleared 9/13/2023 STEVEN WECHSLER
Community Plan Implem. Overlay Cleared 9/28/2023 JOSHUA ORDONEZ
ZI Cleared 9/28/2023 JOSHUA ORDONEZ
Address approval Cleared 10/13/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/14/2023 CARLOS AGUILERA
Sewer availability Cleared 10/14/2023 CARLOS AGUILERA
Low Impact Development (LID) Cleared 2/8/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 2/10/2024 EDGAR ALCARAZ

Contact Information

Contractor Salazar Construction Co Inc; Lic. No.: 491671-B 26306 DIAMOND PLACE STE 100      SANTA CLARITA, CA 91351
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/6/2024 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 5/8/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/21/2024 Partial Approval JENNIFER RABUCHIN
Green Building Rough 5/21/2024 Not Ready for Inspection JENNIFER RABUCHIN
Verify Sprinkler Sign Off 5/21/2024 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/30/2024 Partial Approval JENNIFER RABUCHIN
Green Building Rough 5/30/2024 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 6/27/2024 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 6/27/2024 Not Ready for Inspection JENNIFER RABUCHIN
Sewer 7/19/2024 Partial Inspection JENNIFER RABUCHIN
Underground Mechanical 7/19/2024 Partial Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 8/7/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 8/7/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 8/9/2024 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 9/4/2024 Approved MICHAEL CORTEZ
HVAC-Rough 9/5/2024 Approved KRISTEN CAUSEY
Pre-Inspection 9/24/2024 Approved JENNIFER RABUCHIN
Insulation 9/30/2024 Corrections Issued JENNIFER RABUCHIN
Insulation 10/2/2024 Partial Approval KEVIN BERBERYAN
Drywall Nailing 10/7/2024 Approved JENNIFER RABUCHIN
Green Building Rough 10/7/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/9/2026 Approved JENNIFER RABUCHIN
Final 3/9/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 3/9/2026 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/9/2026 SGSOV Not Required JENNIFER RABUCHIN
Service/Power Release 3/9/2026 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 3/9/2026 Approved JENNIFER RABUCHIN
Final 3/27/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 3/27/2026 Approved JENNIFER RABUCHIN
Service/Power Release 3/27/2026 Not Ready for Inspection JENNIFER RABUCHIN
Final 4/7/2026 OK to Issue CofO JENNIFER RABUCHIN
Service/Power Release 4/7/2026 Not Ready for Inspection JENNIFER RABUCHIN