1050-1052 W 56TH ST 90037
Certificate Information: 1050-1052 W 56TH ST 90037
- Application / Permit
- 23010-20000-03379
- Plan Check / Job No.
- B23VN11318
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ***Eplan.*** NEW 2-STORY DUPLEX WITH ATTACHED GARAGE
- Permit Issued
- Issued on 2/13/2024
- Issuing Office
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2023 | TSE MING HUANG |
| Corrections Issued | 9/11/2023 | TSE MING HUANG |
| Quality Review Completed | 9/12/2023 | KEVIN MORALES |
| Plan Check Approved | 1/16/2024 | TSE MING HUANG |
| Issued | 2/13/2024 | APPLICANT |
| CofO in Progress | 8/26/2024 | SABAS ALONSO |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
| CofO Issued | 9/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/28/2023 | CHRISTINA BRACO |
| Highway dedication | Cleared | 9/28/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 10/3/2023 | CHRISTINA BRACO |
| Low Impact Development (LID) | Cleared | 10/12/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/12/2023 | CHRISTINA BRACO |
| Hydrant and Access approval | Cleared | 10/22/2023 | JOHN CONNEALLY |
| SB8 RUD | Cleared | 11/14/2023 | JULIE LIEU |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/12/2024 | Approved | DAVID FEILER |
| Underground Mechanical | 4/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 4/11/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2024 | Partial Approval | CRAIG DAVIS |
| Insulation | 4/15/2024 | Corrections Issued | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Partial Approval | SABAS ALONSO |
| HVAC-Rough | 6/7/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 6/7/2024 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 6/10/2024 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/10/2024 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 6/10/2024 | Approved | MICHAEL LEWIS |
| Insulation | 6/11/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 6/24/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 6/24/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 6/25/2024 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 7/25/2024 | Conditional Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/23/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 8/23/2024 | Approved | SABAS ALONSO |
| Final | 8/23/2024 | OK to Issue CofO | SABAS ALONSO |
| HVAC-Final | 8/23/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 8/23/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/23/2024 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 8/23/2024 | Approved | SABAS ALONSO |
| Smoke Detectors | 8/23/2024 | Approved | SABAS ALONSO |