20352 W SHERMAN WAY 91306

Certificate Information: 20352 W SHERMAN WAY 91306

Application / Permit
23010-20000-03365
Plan Check / Job No.
B23VN11269
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan NEW 1-STORY SFD "COMPLY WITH DEPARTMENT ORDER effective date 02/15/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". -BLDG SPRINKLERED THRU-OUT
Permit Issued
Issued on 6/11/2024
Issuing Office
Current Status
CofO Issued on 1/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2023 APPLICANT
Assigned to Plan Check Engineer 9/7/2023 MAHNAZ NOURHASHEMI
Corrections Issued 9/16/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 9/27/2023 TU HUA
Applicant returned to address corrections 3/21/2024 CARLOS MONTES
Applicant returned to address corrections 5/19/2024 MAHNAZ NOURHASHEMI
Plan Check Approved 6/3/2024 MAHNAZ NOURHASHEMI
Issued 6/11/2024 APPLICANT
CofO in Progress 1/13/2026 JOEL GUARDADO
Permit Finaled 1/13/2026 DAVID JAMES
CofO Issued 1/13/2026 DAVID JAMES
Permit Finaled 1/13/2026 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 11/15/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 11/20/2023 NIKKI ZULUETA
Sewer availability Cleared 11/20/2023 NIKKI ZULUETA
ZI Cleared 11/20/2023 STEVEN WECHSLER
Hydrant and Access approval Cleared 1/13/2024 RUEL COLE
Low Impact Development (LID) Cleared 2/14/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 2/14/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Kiledjian,, George Zohrab; Lic. No.: C74761 11447 VIKING AVE      NORTHRIDGE, CA 91326

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/5/2024 Partial Inspection JOEL GUARDADO
Excavation/Setback/Form/Re-Bar 9/10/2024 Approved JOEL GUARDADO
Footing/Foundation/Slab 9/10/2024 Approved JOEL GUARDADO
Deputy Wood Construction 9/25/2024 Conditional Approval JOEL GUARDADO
Floor/Roof Diaphrgm/Shear Wall 9/26/2024 Approved JOEL GUARDADO
Wood Frame 9/26/2024 Conditional Approval JOEL GUARDADO
ELECTRICAL-Rough 12/4/2024 Approved JOEL GUARDADO
HVAC-Rough 12/4/2024 Approved JOEL GUARDADO
PLUMBING-Rough 12/4/2024 Not Ready for Inspection JOEL GUARDADO
Interior/Exterior Lathing 12/23/2024 Approved JOEL GUARDADO
PLUMBING-Rough 12/23/2024 Approved JOEL GUARDADO
Wood Frame 12/23/2024 Approved JOEL GUARDADO
PLUMBING-Rough 12/31/2024 Approved JOEL GUARDADO
Wood Frame 12/31/2024 Approved JOEL GUARDADO
Insulation 1/14/2025 Approved JOEL GUARDADO
Drywall Nailing 1/23/2025 Approved JOEL GUARDADO
Shower Pan 1/23/2025 Approved JOEL GUARDADO
Sewer 4/11/2025 No Access for Inspection JOEL GUARDADO
Sewer 4/18/2025 Corrections Issued JOEL GUARDADO
Sewer 5/8/2025 Approved JOEL GUARDADO
Underground Mechanical 5/9/2025 No Access for Inspection JOEL GUARDADO
ELECTRICAL-Final 8/7/2025 Approved JOEL GUARDADO
HVAC-Final 8/7/2025 Partial Inspection JOEL GUARDADO
PLUMBING-Final 8/7/2025 Partial Inspection JOEL GUARDADO
BUILDING-Rough-Frame 10/17/2025 Approved JOEL GUARDADO
Final 10/17/2025 Conditional Approval JOEL GUARDADO
SGSOV-Seismic Gas S/O Valve 10/17/2025 No Access for Inspection JOEL GUARDADO
Service/Power Release 10/17/2025 Approved JOEL GUARDADO
Smoke Detectors 10/17/2025 Approved JOEL GUARDADO
Verify Sprinkler Sign Off 10/17/2025 Approved JOEL GUARDADO
Final 12/2/2025 OK to Issue CofO JOEL GUARDADO
SGSOV-Seismic Gas S/O Valve 12/2/2025 SGSOV Approved JOEL GUARDADO