3926-3926 1/2 S HALLDALE AVE 90062
Certificate Information: 3926-3926 1/2 S HALLDALE AVE 90062
- Application / Permit
- 23010-20000-03352
- Plan Check / Job No.
- B23VN11197
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 35' X 29'-2" (2) DETACHED ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c), (d), and (g)
- Permit Issued
- Issued on 2/1/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2023 | SELLA BENYAMIN |
| Corrections Issued | 8/29/2023 | SELLA BENYAMIN |
| Quality Review Completed | 8/29/2023 | STEVEN KIM |
| Building Plans Picked Up | 8/29/2023 | APPLICANT |
| Applicant returned to address corrections | 12/14/2023 | SELLA BENYAMIN |
| Plan Check Approved | 2/1/2024 | SELLA BENYAMIN |
| Issued | 2/1/2024 | APPLICANT |
| CofO in Progress | 1/15/2025 | SABAS ALONSO |
| Permit Finaled | 1/15/2025 | DEROLD HAUFF |
| CofO Issued | 1/15/2025 | DEROLD HAUFF |
| Permit Finaled | 1/15/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/12/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 9/22/2023 | CHRISTOPHER ROCHA |
| Low Impact Development (LID) | Cleared | 1/19/2024 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 1/22/2024 | JESSICA OPINION |
| Construction near power lines | Cleared | 2/1/2024 | WALTER RAMIREZ |
Contact Information
| Contractor | Nathan D Forte Construction; Lic. No.: 479827-B | 41504 ALMOND AVENUE QUARTZ HILL, CA 93551 |
| Engineer | Sadjadi,, Abdulreza; Lic. No.: C51812 | 1223 WILSHIRE BLVD #169 SANTA MONICA, CA 90403 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/2/2024 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 2/2/2024 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 2/8/2024 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 2/8/2024 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 2/13/2024 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 2/13/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2024 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 3/12/2024 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2024 | Partial Approval | SABAS ALONSO |
| Green Building Rough | 3/12/2024 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 3/12/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 3/14/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/14/2024 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 3/19/2024 | Approved | SABAS ALONSO |
| Sewer | 3/26/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 3/26/2024 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 4/2/2024 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 4/2/2024 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 4/2/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 4/4/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 4/4/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 4/4/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/8/2024 | Partial Approval | JOSH MEISTER |
| BUILDING-Rough-Frame | 4/11/2024 | Approved | SABAS ALONSO |
| Insulation | 4/11/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 4/15/2024 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 4/16/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/26/2024 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 5/1/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 5/24/2024 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 5/24/2024 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 6/5/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 6/6/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 6/6/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 6/11/2024 | Approved | SABAS ALONSO |
| Final | 6/11/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 6/11/2024 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 6/11/2024 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 6/11/2024 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 6/24/2024 | Approved | SABAS ALONSO |
| Masonry Wall/Backfill | 7/1/2024 | Approved | SABAS ALONSO |
| Masonry Wall/Backfill | 7/2/2024 | Approved | SABAS ALONSO |
| Final | 7/23/2024 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 7/23/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 7/23/2024 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 7/23/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 1/3/2025 | Not Ready for Inspection | SABAS ALONSO |
| Service/Power Release | 1/3/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 1/14/2025 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 1/14/2025 | Approved | SABAS ALONSO |