17175 W RAYEN ST 91325

Certificate Information: 17175 W RAYEN ST 91325

Application / Permit
23010-20000-03342
Plan Check / Job No.
B23VN11180
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 6/11/2024
Issuing Office
Current Status
CofO Issued on 6/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2023 APPLICANT
Assigned to Plan Check Engineer 8/25/2023 ALEC MOUSAKHANIAN
Corrections Issued 8/28/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 5/2/2024 ALEC MOUSAKHANIAN
Applicant returned to address corrections 5/13/2024 ALEC MOUSAKHANIAN
Plan Check Approved 6/3/2024 ALEC MOUSAKHANIAN
Issued 6/11/2024 APPLICANT
CofO in Progress 6/4/2025 CHRISTOPHER ROJAS
Permit Finaled 6/6/2025 RUBEN SALAS
CofO Issued 6/6/2025 RUBEN SALAS
Permit Finaled 6/6/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/23/2023 COLIN LOREDO
Sewer availability Cleared 10/30/2023 COLIN LOREDO
Construction near power lines Cleared 12/29/2023 TINA MIRANDA
Low Impact Development (LID) Cleared 4/2/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 4/24/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/25/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/18/2024 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 7/8/2024 Partial Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 7/8/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 7/23/2024 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 7/23/2024 Approved JAVIER RAMOS JR
Insulation 7/23/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 7/23/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 7/25/2024 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/25/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 7/25/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 8/6/2024 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Corrections Issued JAVIER RAMOS JR
Green Building Rough 8/6/2024 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 8/13/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 9/3/2024 Partial Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 9/3/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 9/3/2024 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 11/21/2024 Partial Approval JAVIER RAMOS JR
HVAC-Rough 11/21/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 11/21/2024 Partial Approval JAVIER RAMOS JR
Insulation 12/13/2024 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 12/18/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 12/18/2024 Approved JAVIER RAMOS JR
Green Building Rough 12/18/2024 Approved JAVIER RAMOS JR
Insulation 12/18/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 12/18/2024 Approved JAVIER RAMOS JR
Drywall Nailing 1/22/2025 Approved JAVIER RAMOS JR
Underground Mechanical 2/20/2025 Approved MICHAEL CORTEZ
ELECTRICAL-Final 4/16/2025 Partial Inspection CHRISTOPHER ROJAS
Final 4/16/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 4/16/2025 Partial Inspection CHRISTOPHER ROJAS
HVAC-Final 4/16/2025 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Final 4/16/2025 Partial Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 4/16/2025 SGSOV Not Required CHRISTOPHER ROJAS
Service/Power Release 4/16/2025 Partial Inspection CHRISTOPHER ROJAS
Smoke Detectors 4/16/2025 Partial Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 6/3/2025 Approved CHRISTOPHER ROJAS
Final 6/3/2025 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 6/3/2025 Approved CHRISTOPHER ROJAS
HVAC-Final 6/3/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Final 6/3/2025 Approved CHRISTOPHER ROJAS
Service/Power Release 6/3/2025 Approved CHRISTOPHER ROJAS
Smoke Detectors 6/3/2025 Approved CHRISTOPHER ROJAS