7640 N ORION AVE 91406

Certificate Information: 7640 N ORION AVE 91406

Application / Permit
23010-20000-03317
Plan Check / Job No.
B23VN11081
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) IRR. SHAPED 23'-9" x 40' TWO-STORY SINGLE FAMILY DWELLING [PER SB9]; NFPA-13D THRU-OUT
Permit Issued
Issued on 1/8/2024
Issuing Office
Current Status
CofO Issued on 6/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2023 APPLICANT
Assigned to Plan Check Engineer 8/24/2023 SEAN SHAHMIRI
Corrections Issued 8/28/2023 SEAN SHAHMIRI
Quality Review Completed 8/28/2023 OMID HEDAYAT
Building Plans Picked Up 8/28/2023 APPLICANT
Applicant returned to address corrections 12/18/2023 SEAN SHAHMIRI
Applicant returned to address corrections 1/3/2024 SEAN SHAHMIRI
Plan Check Approved 1/3/2024 SEAN SHAHMIRI
No Progress 1/3/2024 SEAN SHAHMIRI
Plan Check Approved 1/8/2024 SEAN SHAHMIRI
Issued 1/8/2024 APPLICANT
CofO in Progress 5/30/2024 VINCENT HANLEY
Permit Finaled 6/12/2024 RUBEN SALAS
CofO Issued 6/12/2024 RUBEN SALAS
Permit Finaled 6/12/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/28/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 8/29/2023 DAGOVERTO GUERRERO
Senate Bill 9 Cleared 9/6/2023 NATHAN ROMINE
Low Impact Development (LID) Cleared 10/30/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 11/8/2023 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 11/9/2023 NIKKI ZULUETA
Hydrant and Access approval Cleared 1/3/2024 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/19/2024 Partial Approval GREGG CUMMINGS
Sewer 1/19/2024 Approved GREGG CUMMINGS
Underground Mechanical 1/19/2024 Partial Approval GREGG CUMMINGS
Underground Mechanical 1/24/2024 Partial Approval GREGG CUMMINGS
Footing/Foundation/Slab 1/26/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 2/9/2024 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 2/9/2024 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 2/9/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 2/9/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 2/22/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 3/1/2024 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 3/1/2024 Approved CHRISTOPHER ROJAS
Deputy Wood Construction 3/4/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 3/12/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 3/12/2024 Corrections Issued CHRISTOPHER ROJAS
HVAC-Rough 3/12/2024 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 3/12/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/15/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 3/15/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 3/15/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 3/15/2024 Approved CHRISTOPHER ROJAS
MERV13>=Rough 3/15/2024 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 3/15/2024 Approved CHRISTOPHER ROJAS
Insulation 3/19/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 3/26/2024 Approved KIRK SANDERS
Interior/Exterior Lathing 3/26/2024 Approved KIRK SANDERS
Shower Pan 3/26/2024 Approved KIRK SANDERS
ELECTRICAL-Final 5/21/2024 Approved VINCENT HANLEY
HVAC-Final 5/21/2024 Approved VINCENT HANLEY
PLUMBING-Final 5/21/2024 Approved VINCENT HANLEY
Service/Power Release 5/21/2024 Approved VINCENT HANLEY
Final 5/30/2024 OK to Issue CofO VINCENT HANLEY
Green Building Final 5/30/2024 Approved VINCENT HANLEY
MERV13>=Final 5/30/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/30/2024 SGSOV Not Required VINCENT HANLEY
Smoke Detectors 5/30/2024 Approved VINCENT HANLEY