7945 N ETHEL AVE 91605

Certificate Information: 7945 N ETHEL AVE 91605

Application / Permit
23010-20000-03290
Plan Check / Job No.
B23VN10920
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1 STORY DWELLING UNIT WITH ATTACHED GARAGE PER SB9 TWO-UNIT DEVELOPMENT CA GOVT CODE 65852.21 WITH AUTOMATIC SPRINKLERS SYSTEM PER NFPA-13R.
Permit Issued
Issued on 1/3/2024
Issuing Office
Current Status
CofO Issued on 2/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2023 APPLICANT
Assigned to Plan Check Engineer 8/17/2023 ARMEN JIVALAGIAN
Corrections Issued 8/22/2023 ARMEN JIVALAGIAN
Quality Review Completed 8/23/2023 PETER KIM
Applicant returned to address corrections 12/5/2023 ARMEN JIVALAGIAN
Applicant returned to address corrections 12/15/2023 ARMEN JIVALAGIAN
Applicant returned to address corrections 12/19/2023 ARMEN JIVALAGIAN
Applicant returned to address corrections 12/28/2023 ARMEN JIVALAGIAN
Plan Check Approved 12/29/2023 ARMEN JIVALAGIAN
Issued 1/3/2024 APPLICANT
CofO in Progress 1/15/2025 VINCENT HANLEY
Permit Finaled 2/4/2025 RUBEN SALAS
Permit Finaled 2/4/2025 RUBEN SALAS
CofO Issued 2/4/2025 RUBEN SALAS

Permit Application Clearance Information

Senate Bill 9 Cleared 11/13/2023 ALEX VELA
Address approval Cleared 11/14/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 11/14/2023 COLIN LOREDO
Sewer availability Cleared 11/14/2023 COLIN LOREDO
Low Impact Development (LID) Cleared 11/17/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 11/20/2023 NIKKI ZULUETA
Hydrant and Access approval Cleared 12/8/2023 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: NA93079       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/23/2024 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 2/23/2024 Partial Approval GREGG CUMMINGS
Footing/Foundation/Slab 3/1/2024 Corrections Issued WILLIAM WREN
Underground Mechanical 3/4/2024 Not Ready for Inspection DAVID MATSON
Footing/Foundation/Slab 3/6/2024 Not Ready for Inspection GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 3/7/2024 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 3/12/2024 Partial Approval GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 3/14/2024 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 4/5/2024 Partial Approval GREGG CUMMINGS
Deputy Wood Construction 4/12/2024 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 4/12/2024 Partial Approval GREGG CUMMINGS
Deputy Drilled-In Anchors 4/29/2024 Conditional Approval DAVID MATSON
PLUMBING-Rough 4/29/2024 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 5/21/2024 Corrections Issued GREGG CUMMINGS
HVAC-Rough 5/21/2024 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 5/21/2024 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 5/23/2024 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Partial Approval JACK KARGODORIAN
HVAC-Rough 5/23/2024 Approved JACK KARGODORIAN
PLUMBING-Rough 5/23/2024 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 5/23/2024 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 5/28/2024 Not Ready for Inspection GREGG CUMMINGS
Green Building Rough 5/28/2024 Approved GREGG CUMMINGS
Verify Sprinkler Sign Off 5/28/2024 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 6/7/2024 Approved GREGG CUMMINGS
Verify Sprinkler Sign Off 6/7/2024 Approved GREGG CUMMINGS
Sewer 6/24/2024 Approved GREGG CUMMINGS
Underground Mechanical 6/24/2024 Partial Approval GREGG CUMMINGS
Insulation 7/1/2024 Approved DAVID MATSON
Interior/Exterior Lathing 7/1/2024 Partial Approval DAVID MATSON
Shower Pan 7/18/2024 Approved JACK KARGODORIAN
Drywall Nailing 7/25/2024 Approved GREGG CUMMINGS
Interior/Exterior Lathing 7/25/2024 Approved GREGG CUMMINGS
ELECTRICAL-Final 10/9/2024 Not Ready for Inspection GREGG CUMMINGS
Final 10/9/2024 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 10/9/2024 Approved GREGG CUMMINGS
Green Building Final 10/9/2024 Not Ready for Inspection GREGG CUMMINGS
HVAC-Final 10/9/2024 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Final 10/9/2024 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 10/9/2024 SGSOV Not Ready GREGG CUMMINGS
Service/Power Release 10/9/2024 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 10/9/2024 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Final 1/14/2025 Approved VINCENT HANLEY
Final 1/14/2025 OK to Issue CofO VINCENT HANLEY
Green Building Final 1/14/2025 Approved VINCENT HANLEY
HVAC-Final 1/14/2025 Approved VINCENT HANLEY
PLUMBING-Final 1/14/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/14/2025 SGSOV Not Required VINCENT HANLEY
Service/Power Release 1/14/2025 Approved VINCENT HANLEY
Smoke Detectors 1/14/2025 Approved VINCENT HANLEY