631-633 E MARR ST 90291

Certificate Information: 631-633 E MARR ST 90291

Application / Permit
23010-20000-03275
Plan Check / Job No.
B23VN10820
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 32' X 22' -0" TWO ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)1, (d)1, and (g) ALL WORK PER ENGINEERING
Permit Issued
Issued on 2/26/2025
Issuing Office
Valley
Current Status
CofO Issued on 11/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2023 APPLICANT
Assigned to Plan Check Engineer 8/24/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 9/6/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 9/8/2023 OMID HEDAYAT
Building Plans Picked Up 9/18/2023 APPLICANT
Applicant returned to address corrections 1/15/2025 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 1/29/2025 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 2/26/2025 SEWADA ZADOORAN MILAGARDI
Issued 2/26/2025 APPLICANT
CofO in Progress 11/14/2025 JESUS RODRIGUEZ
Permit Finaled 11/20/2025 RICHARD STEINBACH
CofO Issued 11/20/2025 RICHARD STEINBACH
Permit Finaled 11/20/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 10/12/2023 ANDREA SAINT-ANTONIN
Eng Process Fee Ord 176,300 Cleared 10/12/2023 ANDREA SAINT-ANTONIN
Sewer availability Cleared 10/12/2023 ANDREA SAINT-ANTONIN
Specific Plan Cleared 11/30/2023 JOSHUA JONES
Miscellaneous Cleared 12/1/2023 YINGSHI HUANG
Miscellaneous Cleared 12/1/2023 YINGSHI HUANG
Miscellaneous Cleared 12/1/2023 YINGSHI HUANG
Hydrant and Access approval Cleared 1/29/2024 GILBERT URREA
Low Impact Development (LID) Cleared 3/20/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 3/26/2024 ANDREA SAINT-ANTONIN
ZI Cleared 11/4/2024 JACQUELINE TORRES
Coastal Zone Cleared 1/9/2025 DORIAN AGUILAR
Specific Plan Cleared 1/9/2025 DORIAN AGUILAR
ZI Cleared 1/9/2025 DORIAN AGUILAR
ZI Cleared 1/9/2025 DORIAN AGUILAR

Contact Information

Contractor Owner-Builder       ,
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/25/2025 Partial Approval JESUS RODRIGUEZ
Sewer 4/25/2025 Approved JESUS RODRIGUEZ
Underground Mechanical 4/25/2025 Not Ready for Inspection JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/8/2025 Approved MICHAEL ALLEN
Footing/Foundation/Slab 5/8/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 6/5/2025 Corrections Issued JESUS RODRIGUEZ
BUILDING-Rough-Frame 6/11/2025 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 6/11/2025 Approved JESUS RODRIGUEZ
Green Building Rough 6/11/2025 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 6/11/2025 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 6/11/2025 Approved JESUS RODRIGUEZ
Special/Order Compliance 6/11/2025 Partial Inspection JAYLIN GRAVITTE
HVAC-Rough 6/26/2025 Corrections Issued MICHAEL ALLEN
Interior/Exterior Lathing 6/26/2025 Partial Approval MICHAEL ALLEN
Insulation 7/8/2025 Partial Approval MICHAEL ALLEN
Insulation 7/9/2025 Corrections Issued RUBEN RIVAS
Insulation 7/10/2025 Partial Approval JAYLIN GRAVITTE
Drywall Nailing 7/21/2025 Approved JAYLIN GRAVITTE
Green Building Rough 7/21/2025 Approved JAYLIN GRAVITTE
Insulation 7/21/2025 Approved JAYLIN GRAVITTE
Shower Pan 8/14/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 10/15/2025 Corrections Issued WILBER ROSALES
Final 10/15/2025 Corrections Issued WILBER ROSALES
Green Building Final 10/15/2025 Approved WILBER ROSALES
HVAC-Final 10/15/2025 Corrections Issued WILBER ROSALES
PLUMBING-Final 10/15/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV No Gas WILBER ROSALES
Smoke Detectors 10/15/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 11/4/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 11/4/2025 Approved JESUS RODRIGUEZ
Final 11/4/2025 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 11/4/2025 Approved JESUS RODRIGUEZ
Service/Power Release 11/4/2025 Approved JESUS RODRIGUEZ
Final 11/13/2025 OK to Issue CofO JESUS RODRIGUEZ
Service/Power Release 11/13/2025 Approved JESUS RODRIGUEZ