631-633 E MARR ST 90291
Certificate Information: 631-633 E MARR ST 90291
- Application / Permit
- 23010-20000-03275
- Plan Check / Job No.
- B23VN10820
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 32' X 22' -0" TWO ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)1, (d)1, and (g) ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 2/26/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2023 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 9/6/2023 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 9/8/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 9/18/2023 | APPLICANT |
| Applicant returned to address corrections | 1/15/2025 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 1/29/2025 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 2/26/2025 | SEWADA ZADOORAN MILAGARDI |
| Issued | 2/26/2025 | APPLICANT |
| CofO in Progress | 11/14/2025 | JESUS RODRIGUEZ |
| Permit Finaled | 11/20/2025 | RICHARD STEINBACH |
| CofO Issued | 11/20/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/20/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 10/12/2023 | ANDREA SAINT-ANTONIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2023 | ANDREA SAINT-ANTONIN |
| Sewer availability | Cleared | 10/12/2023 | ANDREA SAINT-ANTONIN |
| Specific Plan | Cleared | 11/30/2023 | JOSHUA JONES |
| Miscellaneous | Cleared | 12/1/2023 | YINGSHI HUANG |
| Miscellaneous | Cleared | 12/1/2023 | YINGSHI HUANG |
| Miscellaneous | Cleared | 12/1/2023 | YINGSHI HUANG |
| Hydrant and Access approval | Cleared | 1/29/2024 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 3/20/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/26/2024 | ANDREA SAINT-ANTONIN |
| ZI | Cleared | 11/4/2024 | JACQUELINE TORRES |
| Coastal Zone | Cleared | 1/9/2025 | DORIAN AGUILAR |
| Specific Plan | Cleared | 1/9/2025 | DORIAN AGUILAR |
| ZI | Cleared | 1/9/2025 | DORIAN AGUILAR |
| ZI | Cleared | 1/9/2025 | DORIAN AGUILAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/25/2025 | Partial Approval | JESUS RODRIGUEZ |
| Sewer | 4/25/2025 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 4/25/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 5/8/2025 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 5/8/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2025 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 6/11/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 6/11/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 6/11/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 6/11/2025 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 6/11/2025 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 6/11/2025 | Partial Inspection | JAYLIN GRAVITTE |
| HVAC-Rough | 6/26/2025 | Corrections Issued | MICHAEL ALLEN |
| Interior/Exterior Lathing | 6/26/2025 | Partial Approval | MICHAEL ALLEN |
| Insulation | 7/8/2025 | Partial Approval | MICHAEL ALLEN |
| Insulation | 7/9/2025 | Corrections Issued | RUBEN RIVAS |
| Insulation | 7/10/2025 | Partial Approval | JAYLIN GRAVITTE |
| Drywall Nailing | 7/21/2025 | Approved | JAYLIN GRAVITTE |
| Green Building Rough | 7/21/2025 | Approved | JAYLIN GRAVITTE |
| Insulation | 7/21/2025 | Approved | JAYLIN GRAVITTE |
| Shower Pan | 8/14/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 10/15/2025 | Corrections Issued | WILBER ROSALES |
| Final | 10/15/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Final | 10/15/2025 | Approved | WILBER ROSALES |
| HVAC-Final | 10/15/2025 | Corrections Issued | WILBER ROSALES |
| PLUMBING-Final | 10/15/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 10/15/2025 | SGSOV No Gas | WILBER ROSALES |
| Smoke Detectors | 10/15/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 11/4/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 11/4/2025 | Approved | JESUS RODRIGUEZ |
| Final | 11/4/2025 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 11/4/2025 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 11/4/2025 | Approved | JESUS RODRIGUEZ |
| Final | 11/13/2025 | OK to Issue CofO | JESUS RODRIGUEZ |
| Service/Power Release | 11/13/2025 | Approved | JESUS RODRIGUEZ |