6013-6015 N COLFAX AVE 91606

Certificate Information: 6013-6015 N COLFAX AVE 91606

Application / Permit
23010-20000-03242
Plan Check / Job No.
B23VN10748
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Addition to (E) SFD and conversion to duplex per SB 9
Permit Issued
Issued on 5/25/2024
Issuing Office
Current Status
Issued on 5/25/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/13/2023 APPLICANT
Assigned to Plan Check Engineer 8/31/2023 HOOMAN HAJIZADEH
Corrections Issued 9/12/2023 HOOMAN HAJIZADEH
Quality Review Completed 9/21/2023 KAVIAN REFAHI
Applicant returned to address corrections 3/22/2024 HOOMAN HAJIZADEH
Applicant returned to address corrections 4/19/2024 HOOMAN HAJIZADEH
Plan Check Approved 5/24/2024 HOOMAN HAJIZADEH
Issued 5/25/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/1/2023 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 11/7/2023 EDGAR ALCARAZ
Sewer availability Cleared 11/7/2023 EDGAR ALCARAZ
Senate Bill 9 Cleared 12/12/2023 BRENNEN OBETO
Tenant Habitability Plan Cleared 12/14/2023 RICARDO BOHORQUEZ
Low Impact Development (LID) Cleared 12/15/2023 TOMMY YIN
Hydrant and Access approval Cleared 1/12/2024 GILBERT URREA
Roof/Waste drainage to street Cleared 1/12/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: NA56881       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/26/2024 Approved ROBERTO PALACIOS-LOPEZ
Pre-Inspection 7/12/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 8/13/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 9/13/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 9/20/2024 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/18/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Green Building Rough 10/18/2024 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/5/2024 Partial Approval JOSE AVILA
ELECTRICAL-Rough 1/27/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 1/27/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 1/27/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/28/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Green Building Rough 1/28/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 1/31/2025 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 1/31/2025 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 1/31/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 1/31/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 1/31/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/27/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 2/27/2025 Conditional Approval ROBERTO PALACIOS-LOPEZ
Green Building Rough 2/27/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 2/27/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/27/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/9/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 4/9/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 4/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 6/2/2025 Not Ready for Inspection MICHAEL CORTEZ
Interior/Exterior Lathing 6/2/2025 Approved MICHAEL CORTEZ
Drywall Nailing 6/6/2025 Corrections Issued MISAEL ESPARZA
Drywall Nailing 6/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 6/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 6/12/2025 Approved LOUIS ESCOTO