16448 W LASSEN ST 91343
Certificate Information: 16448 W LASSEN ST 91343
- Application / Permit
- 23010-20000-03238
- Plan Check / Job No.
- B23VN10740
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 24'-6" X 25' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 11/8/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2023 | SELLA BENYAMIN |
| Corrections Issued | 8/21/2023 | SELLA BENYAMIN |
| Quality Review Completed | 8/21/2023 | STEVEN KIM |
| Building Plans Picked Up | 8/22/2023 | APPLICANT |
| Plan Check Approved | 11/7/2024 | SELLA BENYAMIN |
| Issued | 11/8/2024 | APPLICANT |
| CofO in Progress | 4/13/2026 | KIRK SANDERS |
| Permit Finaled | 5/21/2026 | RUBEN SALAS |
| CofO Issued | 5/21/2026 | RUBEN SALAS |
| Permit Finaled | 5/21/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/11/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 9/18/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2023 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 2/5/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 5/31/2024 | JOHN LIN |
| Construction within easement | Cleared | 7/5/2024 | WALTER RAMIREZ |
| GPI Written Notices | Cleared | 7/24/2024 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 7/24/2024 | SELLA BENYAMIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/11/2025 | Conditional Approval | RAUL OLAGI |
| PLUMBING-Rough | 2/11/2025 | Partial Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 2/24/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 2/26/2025 | Conditional Approval | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2025 | Partial Approval | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 6/16/2025 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 6/16/2025 | Corrections Issued | DAVID ANDERSON |
| Green Building Rough | 6/16/2025 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 6/16/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 6/16/2025 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 7/14/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 7/14/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 7/14/2025 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 7/14/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 7/23/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 7/28/2025 | Partial Approval | MISAEL ESPARZA |
| Insulation | 8/6/2025 | Approved | DAVID ANDERSON |
| Drywall Nailing | 8/26/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 9/15/2025 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 10/2/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 10/2/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 12/12/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 12/12/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 12/12/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Final | 12/12/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 12/12/2025 | Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 12/12/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 12/12/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 3/26/2026 | Not Ready for Inspection | KIRK SANDERS |
| Service/Power Release | 3/26/2026 | Not Ready for Inspection | KIRK SANDERS |
| Final | 4/13/2026 | OK to Issue CofO | KIRK SANDERS |
| Service/Power Release | 4/13/2026 | Approved | KIRK SANDERS |