17181-17183 W MCKEEVER ST 91344
Certificate Information: 17181-17183 W MCKEEVER ST 91344
- Application / Permit
- 23010-20000-03222
- Plan Check / Job No.
- B23VN10676
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 52' X 38' SINGLE FAMILY DWELLING PER SB-9 AND ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
- Permit Issued
- Issued on 8/9/2024
- Issuing Office
- Current Status
- CofO Issued on 6/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2023 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 8/29/2023 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 9/1/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 6/27/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 7/30/2024 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 8/1/2024 | SEWADA ZADOORAN MILAGARDI |
| Issued | 8/9/2024 | APPLICANT |
| CofO in Progress | 4/15/2025 | DAVID SCANTLIN |
| CofO in Progress | 5/16/2025 | STEVEN BACK |
| CofO in Progress | 6/25/2025 | STEVEN BACK |
| Permit Finaled | 6/27/2025 | JOHN JANSON |
| CofO Issued | 6/27/2025 | JOHN JANSON |
| Permit Finaled | 6/27/2025 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/30/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/30/2024 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 3/8/2024 | JOHN CONNEALLY |
| Senate Bill 9 | Cleared | 5/24/2024 | DORIAN AGUILAR |
| Address approval | Cleared | 5/29/2024 | KENIA CASTILLO |
| Low Impact Development (LID) | Cleared | 5/31/2024 | ANDRES COVARRUBIAS |
| Sewer availability | Cleared | 6/3/2024 | KENIA CASTILLO |
| Roof/Waste drainage to street | Cleared | 6/6/2024 | KENIA CASTILLO |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2024 | KENIA CASTILLO |
| GPI Written Notices | Cleared | 7/30/2024 | SEWADA ZADOORAN MILAGARDI |
| Grading Pre-Inspection | Cleared | 7/30/2024 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/22/2024 | Partial Inspection | STEVEN BACK |
| PLUMBING-Rough | 8/27/2024 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 9/5/2024 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2024 | Approved | STEVEN BACK |
| HVAC-Rough | 10/18/2024 | Approved | STEVEN BACK |
| PLUMBING-Rough | 10/18/2024 | Partial Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 10/22/2024 | Partial Approval | SCOTT SOBEL |
| Interior/Exterior Lathing | 11/1/2024 | Partial Inspection | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 11/12/2024 | Approved | STEVEN BACK |
| PLUMBING-Rough | 11/12/2024 | Approved | STEVEN BACK |
| Sewer | 11/22/2024 | Approved | STEVEN BACK |
| Underground Mechanical | 11/22/2024 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 12/5/2024 | Approved | STEVEN BACK |
| Green Building Rough | 12/5/2024 | Approved | STEVEN BACK |
| MERV13>=Rough | 12/5/2024 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 12/5/2024 | Approved | STEVEN BACK |
| Insulation | 12/11/2024 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 12/16/2024 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 1/17/2025 | Partial Approval | STEVEN BACK |
| Final | 3/19/2025 | Corrections Issued | STEVEN BACK |
| Green Building Final | 3/19/2025 | Approved | STEVEN BACK |
| MERV13>=Final | 3/19/2025 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 3/19/2025 | SGSOV Not Required | STEVEN BACK |
| Service/Power Release | 3/19/2025 | Not Ready for Inspection | STEVEN BACK |
| Smoke Detectors | 3/19/2025 | Approved | STEVEN BACK |
| Final | 4/14/2025 | Corrections Issued | DAVID SCANTLIN |
| Service/Power Release | 4/14/2025 | Approved | DAVID SCANTLIN |
| Final | 5/16/2025 | Corrections Issued | STEVEN BACK |
| Final | 6/25/2025 | OK to Issue CofO | STEVEN BACK |