5102 N ETIWANDA AVE 91356
Certificate Information: 5102 N ETIWANDA AVE 91356
- Application / Permit
- 23010-20000-03216
- Plan Check / Job No.
- B23VN10654
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW IRREGULAR SHAPED 49' X 32'-4" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 11/12/2025
- Issuing Office
- Current Status
- Issued on 11/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2023 | JESSE ARELLANO |
| Corrections Issued | 8/16/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 8/17/2023 | APPLICANT |
| Applicant returned to address corrections | 2/8/2024 | ANGELICA DAVE |
| Plan Check Approved | 3/1/2024 | SARKIS HARABEDIAN |
| Issued | 11/12/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/31/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 12/15/2023 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 12/26/2023 | SERGIO VALENZUELA |
| Low Impact Development (LID) | Cleared | 12/27/2023 | MELINEH AGHAKHABIAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/29/2024 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 3/1/2024 | JESSE ARELLANO |
| Roof/Waste drainage to street | Cleared | 3/1/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 3/1/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Evergreen Construction Group Inc; Lic. No.: 998238-B | 6444 BELLINGHAM AVE #204 NORTH HOLLYWOOD, CA 91606 |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/12/2026 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 1/20/2026 | Conditional Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 2/10/2026 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 2/10/2026 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 2/10/2026 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 2/13/2026 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 2/13/2026 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 2/13/2026 | Not Ready for Inspection | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2026 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 3/9/2026 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 3/13/2026 | Corrections Issued | MORRIS JACKSON |
| ELECTRICAL-Rough | 3/13/2026 | Corrections Issued | MORRIS JACKSON |
| Green Building Rough | 3/13/2026 | Approved | MORRIS JACKSON |
| HVAC-Rough | 3/13/2026 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 3/13/2026 | Partial Approval | MORRIS JACKSON |
| PLUMBING-Rough | 3/13/2026 | Approved | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 3/13/2026 | Partial Inspection | MORRIS JACKSON |
| Interior/Exterior Lathing | 3/16/2026 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 3/18/2026 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 3/18/2026 | Approved | JOHN KIDWELL |
| HVAC-Rough | 3/18/2026 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 3/18/2026 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 3/18/2026 | Approved | JOHN KIDWELL |
| Gas Test | 3/26/2026 | Partial Approval | JOHN KIDWELL |
| Insulation | 3/26/2026 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Not Ready | JOHN KIDWELL |
| Sewer | 3/26/2026 | Approved | JOHN KIDWELL |
| Drywall Nailing | 3/31/2026 | Approved | JOHN KIDWELL |
| Shower Pan | 3/31/2026 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 4/14/2026 | Partial Approval | JOHN KIDWELL |
| Final | 6/4/2026 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 6/4/2026 | Approved | JOHN KIDWELL |
| Green Building Final | 6/4/2026 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 6/4/2026 | SGSOV Not Ready | JOHN KIDWELL |
| Service/Power Release | 6/4/2026 | Not Ready for Inspection | JOHN KIDWELL |
| Smoke Detectors | 6/4/2026 | Approved | JOHN KIDWELL |