14519 W GREENLEAF ST 91403

Certificate Information: 14519 W GREENLEAF ST 91403

Application / Permit
23010-20000-03202
Plan Check / Job No.
B23VN10606
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 38' X 63' IRREGULAR SHAPED 2-STORY SFD W/ 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 1/25/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/8/2023 APPLICANT
Assigned to Plan Check Engineer 8/10/2023 RAPHAEL ROSAS
Corrections Issued 8/14/2023 RAPHAEL ROSAS
Quality Review Completed 8/15/2023 STEVEN KIM
Building Plans Picked Up 8/16/2023 APPLICANT
Applicant returned to address corrections 11/22/2023 RAPHAEL ROSAS
Applicant returned to address corrections 11/28/2023 RAPHAEL ROSAS
Applicant returned to address corrections 12/19/2023 RAPHAEL ROSAS
Plan Check Approved 1/24/2024 RAPHAEL ROSAS
Issued 1/25/2024 APPLICANT
CofO in Progress 9/16/2025 MISAEL ESPARZA
CofO Issued 9/25/2025 RUBEN SALAS
Permit Finaled 9/25/2025 RUBEN SALAS

Permit Application Clearance Information

Trees in Parkway Cleared 9/8/2023 ADALBERTO VERA
Low Impact Development (LID) Cleared 10/13/2023 MELINEH AGHAKHABIAN
Address approval Cleared 10/17/2023 LEE GUILBEAUX
Permit Cleared 10/17/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/18/2023 LEE GUILBEAUX
Sewer availability Cleared 10/18/2023 LEE GUILBEAUX
Hydrant and Access approval Cleared 10/27/2023 LAVEON RIDER
Roof/Waste drainage to street Cleared 11/1/2023 LEE GUILBEAUX
GPI Written Notices Cleared 1/24/2024 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 1/24/2024 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 3/19/2024 Approved MISAEL ESPARZA
Footing/Foundation/Slab 3/19/2024 Partial Inspection MISAEL ESPARZA
Pre-Inspection 3/19/2024 Approved MISAEL ESPARZA
Deputy Reinf. Concrete 5/9/2024 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 6/3/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 6/5/2024 Partial Approval MISAEL ESPARZA
Pre-Inspection 6/5/2024 Partial Inspection MISAEL ESPARZA
Footing/Foundation/Slab 6/27/2024 Partial Approval JOHN COLEMAN
Footing/Foundation/Slab 7/3/2024 Partial Approval KEVIN BERBERYAN
Underground Mechanical 7/22/2024 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 7/26/2024 Approved VINCENT HANLEY
Deputy Steel/Welding 9/30/2024 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 10/9/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Corrections Issued MISAEL ESPARZA
Deputy Steel/Welding 11/7/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/26/2024 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/31/2024 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 1/2/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 1/3/2025 Corrections Issued JACK KARGODORIAN
HVAC-Rough 1/3/2025 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 1/8/2025 Approved MISAEL ESPARZA
HVAC-Rough 1/8/2025 Conditional Approval MISAEL ESPARZA
PLUMBING-Rough 1/8/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 1/14/2025 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/24/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 1/24/2025 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 1/31/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 1/31/2025 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 1/31/2025 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 2/5/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 2/6/2025 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 2/10/2025 Corrections Issued MISAEL ESPARZA
Green Building Rough 2/10/2025 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 2/10/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 2/12/2025 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 2/12/2025 Approved MISAEL ESPARZA
Insulation 2/18/2025 Partial Approval MISAEL ESPARZA
Drywall Nailing 2/26/2025 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 3/24/2025 Approved MISAEL ESPARZA
Drywall Nailing 3/24/2025 Approved MISAEL ESPARZA
Insulation 3/24/2025 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 4/2/2025 Approved MISAEL ESPARZA
Sewer 4/2/2025 Partial Approval MISAEL ESPARZA
Sewer 4/7/2025 Not Ready for Inspection JUAN VALENZUELA
Sewer 4/14/2025 Approved MISAEL ESPARZA
ELECTRICAL-Final 6/16/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 6/20/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 6/27/2025 Not Ready for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Final 7/1/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 7/1/2025 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 7/3/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
HVAC-Final 7/10/2025 Approved MISAEL ESPARZA
PLUMBING-Final 7/10/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 7/15/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 7/18/2025 Approved MISAEL ESPARZA
Final 9/12/2025 OK to Issue CofO MISAEL ESPARZA
Green Building Final 9/12/2025 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Not Required MISAEL ESPARZA
Service/Power Release 9/12/2025 Approved MISAEL ESPARZA
Smoke Detectors 9/12/2025 Approved MISAEL ESPARZA