13312-13314 W ERWIN ST 91401

Certificate Information: 13312-13314 W ERWIN ST 91401

Application / Permit
23010-20000-03193
Plan Check / Job No.
B23VN10572
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 32' 8" x 51' 6" two story detached SB9 and ADU, first story of SB9 and attached ADU, and 2nd story ADU, with attached trellis in the back. NFPA 13D sprinkler is required. All work done per engineering.
Permit Issued
Issued on 4/16/2024
Issuing Office
Current Status
CofO Issued on 3/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/8/2023 APPLICANT
Assigned to Plan Check Engineer 8/24/2023 NAREG ATARIAN
Corrections Issued 8/29/2023 NAREG ATARIAN
Quality Review Completed 8/30/2023 OMID HEDAYAT
Building Plans Picked Up 9/1/2023 APPLICANT
Applicant returned to address corrections 1/18/2024 NAREG ATARIAN
Plan Check Approved 2/14/2024 NAREG ATARIAN
Issued 4/16/2024 APPLICANT
CofO in Progress 2/25/2025 OGANES TARAKHCHYAN
Permit Finaled 3/3/2025 RUBEN SALAS
CofO Issued 3/3/2025 RUBEN SALAS
Permit Finaled 3/3/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/7/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 9/8/2023 DAGOVERTO GUERRERO
Low Impact Development (LID) Cleared 10/6/2023 LUIS LUVANO
Hydrant and Access approval Cleared 10/8/2023 JOHN CONNEALLY
Senate Bill 9 Cleared 10/11/2023 ASHLEY RODARTE
Roof/Waste drainage to street Cleared 10/12/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/18/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/22/2024 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 7/31/2024 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 8/5/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/29/2024 Partial Approval OGANES TARAKHCHYAN
Pre-Inspection 8/30/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/9/2024 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 10/9/2024 Approved OGANES TARAKHCHYAN
Green Building Rough 10/9/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 10/9/2024 Corrections Issued OGANES TARAKHCHYAN
Interior/Exterior Lathing 10/9/2024 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 10/9/2024 Approved OGANES TARAKHCHYAN
Pre-Inspection 10/9/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 10/9/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/11/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 10/11/2024 Approved OGANES TARAKHCHYAN
Insulation 10/15/2024 Approved GAREN HAYRAPETYAN
Shower Pan 10/15/2024 Approved GAREN HAYRAPETYAN
Drywall Nailing 10/21/2024 Approved GAREN HAYRAPETYAN
Final 1/30/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 1/30/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Rough-Elec/Plmb/HVAC 1/30/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 1/30/2025 SGSOV No Gas GAREN HAYRAPETYAN
Service/Power Release 1/30/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Smoke Detectors 1/30/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 2/20/2025 Approved OGANES TARAKHCHYAN
Final 2/20/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 2/20/2025 Approved OGANES TARAKHCHYAN
HVAC-Final 2/20/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Final 2/20/2025 Approved OGANES TARAKHCHYAN
Service/Power Release 2/20/2025 Approved OGANES TARAKHCHYAN
Final 2/24/2025 OK to Issue CofO OGANES TARAKHCHYAN
Service/Power Release 2/24/2025 Approved OGANES TARAKHCHYAN