7126 N MCLENNAN AVE 91406

Certificate Information: 7126 N MCLENNAN AVE 91406

Application / Permit
23010-20000-03172
Plan Check / Job No.
B23VN10483
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRREGULAR SHAPED 69' 6" X 60' 11" ONE STORY SFD WITH ATTACHED GARAGE AND ATTACHED TRELLIS WITH NFPA 13D SPRINKLER REQUIRED THROUGHOUT. ALL WORK DONE PER ENGINEER.
Permit Issued
Issued on 11/7/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2023 APPLICANT
Assigned to Plan Check Engineer 8/17/2023 NAREG ATARIAN
Corrections Issued 8/18/2023 NAREG ATARIAN
Quality Review Completed 8/18/2023 OMID HEDAYAT
Building Plans Picked Up 8/21/2023 APPLICANT
Plan Check Approved 11/6/2023 NAREG ATARIAN
Issued 11/7/2023 APPLICANT
CofO in Progress 2/9/2026 GAREN HAYRAPETYAN
Permit Finaled 3/3/2026 RUBEN SALAS
CofO Issued 3/3/2026 RUBEN SALAS
Permit Finaled 3/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/25/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 8/25/2023 TAL SHEMEN
Permit Cleared 8/25/2023 TAL SHEMEN
Sewer availability Cleared 8/25/2023 TAL SHEMEN
Low Impact Development (LID) Cleared 10/24/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 10/26/2023 EDGAR ALCARAZ
Frnt yard landscape/Water mgmt Cleared 10/30/2023 GEORGIA SMITH

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/29/2024 Approved RAUL OLAGI
Excavation/Setback/Form/Re-Bar 3/12/2024 Not Ready for Inspection RAUL OLAGI
Underground Mechanical 3/12/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 3/13/2024 Partial Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 3/21/2024 Not Ready for Inspection RAUL OLAGI
Footing/Foundation/Slab 3/21/2024 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 3/26/2024 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 3/29/2024 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/23/2024 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 8/20/2024 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 8/20/2024 Approved RAUL OLAGI
HVAC-Rough 8/20/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 8/20/2024 Corrections Issued RAUL OLAGI
Verify Sprinkler Sign Off 8/20/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 8/28/2024 Partial Approval RAUL OLAGI
HVAC-Rough 8/28/2024 Approved RAUL OLAGI
PLUMBING-Rough 8/28/2024 Approved RAUL OLAGI
Verify Sprinkler Sign Off 8/28/2024 Approved RAUL OLAGI
Insulation 9/10/2024 Not Ready for Inspection RAUL OLAGI
Sewer 9/10/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 10/17/2024 Approved SALVADOR MARTINEZ
Insulation 10/17/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 10/17/2024 Partial Approval SALVADOR MARTINEZ
Drywall Nailing 10/25/2024 Approved GAREN HAYRAPETYAN
Green Building Rough 10/25/2024 Approved GAREN HAYRAPETYAN
Shower Pan 2/21/2025 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 4/17/2025 Approved SALVADOR MARTINEZ
Final 10/24/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 10/24/2025 Not Ready for Inspection GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV No Gas GAREN HAYRAPETYAN
Service/Power Release 10/24/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Smoke Detectors 10/24/2025 Approved GAREN HAYRAPETYAN
Final 2/5/2026 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 2/5/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Service/Power Release 2/5/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Final 2/9/2026 OK to Issue CofO GAREN HAYRAPETYAN
Green Building Final 2/9/2026 Approved GAREN HAYRAPETYAN
Service/Power Release 2/9/2026 Approved GAREN HAYRAPETYAN