7421 N BLEWETT AVE 91406
Certificate Information: 7421 N BLEWETT AVE 91406
- Application / Permit
- 23010-20000-03167
- Plan Check / Job No.
- B23VN10474
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: New Detached 1-Story ADU per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 2/22/2024
- Issuing Office
- Current Status
- CofO Issued on 2/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2023 | DAVID CASTILLO |
| Corrections Issued | 8/10/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 11/29/2023 | DAVID CASTILLO |
| Plan Check Approved | 11/30/2023 | ALFREDO JARA |
| Issued | 2/22/2024 | APPLICANT |
| CofO in Progress | 2/11/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 2/19/2025 | RUBEN SALAS |
| CofO Issued | 2/19/2025 | RUBEN SALAS |
| Permit Finaled | 2/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/20/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 11/20/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 11/20/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 11/20/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 11/22/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Adu Rc Builders; Lic. No.: 1080967-B | , |
| Contractor | Ca Construction Group Inc; Lic. No.: 1080967-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: NA93079 | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/28/2024 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 2/28/2024 | Partial Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 3/4/2024 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 3/4/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/13/2024 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 5/13/2024 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2024 | Approved | RAUL OLAGI |
| HVAC-Rough | 5/13/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 5/13/2024 | Corrections Issued | RAUL OLAGI |
| Sewer | 5/13/2024 | Approved | RAUL OLAGI |
| Underground Mechanical | 5/13/2024 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 5/13/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 6/7/2024 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/21/2024 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 6/21/2024 | Approved | RAUL OLAGI |
| HVAC-Rough | 6/21/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 6/21/2024 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 6/21/2024 | Approved | RAUL OLAGI |
| Insulation | 7/1/2024 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 7/3/2024 | Approved | RAUL OLAGI |
| Green Building Rough | 7/3/2024 | Approved | RAUL OLAGI |
| Insulation | 7/3/2024 | Corrections Issued | RAUL OLAGI |
| Insulation | 7/10/2024 | Approved | RAUL OLAGI |
| Drywall Nailing | 7/22/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 8/8/2024 | Approved | LOUIS ESCOTO |
| Shower Pan | 8/8/2024 | Approved | LOUIS ESCOTO |
| ELECTRICAL-Final | 11/25/2024 | Corrections Issued | RAUL OLAGI |
| Final | 11/25/2024 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 11/25/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 11/25/2024 | Corrections Issued | RAUL OLAGI |
| Smoke Detectors | 11/25/2024 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 1/23/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 2/7/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Green Building Final | 2/7/2025 | Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 2/7/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Final | 2/11/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Service/Power Release | 2/11/2025 | Approved | GAREN HAYRAPETYAN |