7421 N BLEWETT AVE 91406

Certificate Information: 7421 N BLEWETT AVE 91406

Application / Permit
23010-20000-03167
Plan Check / Job No.
B23VN10474
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: New Detached 1-Story ADU per LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 2/22/2024
Issuing Office
Current Status
CofO Issued on 2/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2023 APPLICANT
Assigned to Plan Check Engineer 8/9/2023 DAVID CASTILLO
Corrections Issued 8/10/2023 DAVID CASTILLO
Applicant returned to address corrections 11/29/2023 DAVID CASTILLO
Plan Check Approved 11/30/2023 ALFREDO JARA
Issued 2/22/2024 APPLICANT
CofO in Progress 2/11/2025 GAREN HAYRAPETYAN
Permit Finaled 2/19/2025 RUBEN SALAS
CofO Issued 2/19/2025 RUBEN SALAS
Permit Finaled 2/19/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/20/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 11/20/2023 NIKKI ZULUETA
Low Impact Development (LID) Cleared 11/20/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 11/20/2023 NIKKI ZULUETA
Sewer availability Cleared 11/20/2023 NIKKI ZULUETA
Construction near power lines Cleared 11/22/2023 RIDWAN HARDY

Contact Information

Contractor Adu Rc Builders; Lic. No.: 1080967-B       ,
Contractor Ca Construction Group Inc; Lic. No.: 1080967-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: NA93079       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/28/2024 Partial Approval RAUL OLAGI
PLUMBING-Rough 2/28/2024 Partial Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 3/4/2024 Approved RAUL OLAGI
Footing/Foundation/Slab 3/4/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 5/13/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 5/13/2024 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/13/2024 Approved RAUL OLAGI
HVAC-Rough 5/13/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 5/13/2024 Corrections Issued RAUL OLAGI
Sewer 5/13/2024 Approved RAUL OLAGI
Underground Mechanical 5/13/2024 Approved RAUL OLAGI
Verify Sprinkler Sign Off 5/13/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 6/7/2024 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 6/21/2024 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 6/21/2024 Approved RAUL OLAGI
HVAC-Rough 6/21/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 6/21/2024 Partial Approval RAUL OLAGI
PLUMBING-Rough 6/21/2024 Approved RAUL OLAGI
Insulation 7/1/2024 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 7/3/2024 Approved RAUL OLAGI
Green Building Rough 7/3/2024 Approved RAUL OLAGI
Insulation 7/3/2024 Corrections Issued RAUL OLAGI
Insulation 7/10/2024 Approved RAUL OLAGI
Drywall Nailing 7/22/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 8/8/2024 Approved LOUIS ESCOTO
Shower Pan 8/8/2024 Approved LOUIS ESCOTO
ELECTRICAL-Final 11/25/2024 Corrections Issued RAUL OLAGI
Final 11/25/2024 Corrections Issued RAUL OLAGI
HVAC-Final 11/25/2024 Corrections Issued RAUL OLAGI
PLUMBING-Final 11/25/2024 Corrections Issued RAUL OLAGI
Smoke Detectors 11/25/2024 Approved RAUL OLAGI
ELECTRICAL-Final 1/23/2025 Approved GAREN HAYRAPETYAN
Final 2/7/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Green Building Final 2/7/2025 Approved GAREN HAYRAPETYAN
Service/Power Release 2/7/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Final 2/11/2025 OK to Issue CofO GAREN HAYRAPETYAN
Service/Power Release 2/11/2025 Approved GAREN HAYRAPETYAN