889-889 1/2 E 35TH ST 90011

Certificate Information: 889-889 1/2 E 35TH ST 90011

Application / Permit
23010-20000-03111
Plan Check / Job No.
B23VN10246
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN NEW (2) 18'-7 9/16" X 42' ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/12/2024
Issuing Office
Current Status
CofO Issued on 4/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2023 APPLICANT
Assigned to Plan Check Engineer 8/17/2023 RAPHAEL ROSAS
Corrections Issued 8/22/2023 RAPHAEL ROSAS
Quality Review Completed 8/25/2023 STEVEN KIM
Applicant returned to address corrections 11/6/2023 RAPHAEL ROSAS
Applicant returned to address corrections 11/16/2023 RAPHAEL ROSAS
Applicant returned to address corrections 11/21/2023 RAPHAEL ROSAS
Applicant returned to address corrections 12/11/2023 RAPHAEL ROSAS
Plan Check Approved 1/3/2024 RAPHAEL ROSAS
Issued 8/12/2024 APPLICANT
CofO in Progress 4/14/2025 ALEJANDRO DE ARTOLA
Permit Finaled 4/14/2025 DEROLD HAUFF
CofO Issued 4/14/2025 DEROLD HAUFF
Permit Finaled 4/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/6/2023 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 9/6/2023 AMBER CAMPBELL
Sewer availability Cleared 9/6/2023 AMBER CAMPBELL
Tenant Habitability Plan Cleared 10/4/2023 RICARDO BOHORQUEZ
Low Impact Development (LID) Cleared 11/16/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 11/16/2023 DAVID LOPEZ
Construction near power lines Cleared 12/26/2023 RIDWAN HARDY

Contact Information

Contractor Mr Build Home Improvement Company; Lic. No.: 439166-B       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/29/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 8/29/2024 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 8/29/2024 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 8/30/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 8/30/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Underground Mechanical 8/30/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/3/2024 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 9/3/2024 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 9/5/2024 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/5/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/6/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 9/6/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/24/2024 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 9/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/24/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 9/26/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 9/26/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/26/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/30/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 9/30/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/2/2024 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 10/2/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/2/2024 Partial Approval ALEJANDRO DE ARTOLA
Sewer 10/3/2024 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 10/8/2024 Approved ALEJANDRO DE ARTOLA
Sewer 10/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/23/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 12/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 12/23/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 12/23/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 12/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 12/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/6/2025 Approved ALEJANDRO DE ARTOLA
Final 2/6/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 2/6/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 2/6/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 2/6/2025 SGSOV Not Required ALEJANDRO DE ARTOLA
Service/Power Release 2/6/2025 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 2/6/2025 Approved ALEJANDRO DE ARTOLA
Final 4/11/2025 OK to Issue CofO ALEJANDRO DE ARTOLA