228 W 43RD PL 90037

Certificate Information: 228 W 43RD PL 90037

Application / Permit
23010-20000-03103
Plan Check / Job No.
B23VN10203
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: CONVERT EXISITNG DETACHED 2-CAR GARAGE WITH GROUND ADDITON TO CREATE 1-STORY ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 11/25/2023
Issuing Office
Current Status
Issued on 11/25/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/1/2023 APPLICANT
Assigned to Plan Check Engineer 8/17/2023 MICHAEL LOPEZ
Corrections Issued 8/18/2023 KHEDER ALRAZAA
Quality Review Completed 9/5/2023 PRANITA SHAH
Applicant returned to address corrections 10/24/2023 MICHAEL LOPEZ
Plan Check Approved 11/13/2023 MICHAEL LOPEZ
Issued 11/25/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/21/2023 JESSICA OPINION
Community Plan Implem. Overlay Cleared 9/21/2023 HELEN JADALI
Eng Process Fee Ord 176,300 Cleared 9/21/2023 JESSICA OPINION
Roof/Waste drainage to street Cleared 9/21/2023 JESSICA OPINION
Sewer availability Cleared 9/21/2023 JESSICA OPINION

Contact Information

Contractor Owner-Builder       ,
Engineer Mirzadeh,, Amir; Lic. No.: C58119 P O BOX 572110      TARZANA, CA 91357

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 3/4/2024 Approved MICHAEL LEWIS
Underground Mechanical 3/4/2024 Corrections Issued MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 3/13/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/13/2024 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 5/29/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/3/2024 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 10/10/2024 Approved CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 11/12/2024 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 1/30/2025 Approved SABAS ALONSO
Green Building Rough 1/30/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 1/30/2025 Partial Approval SABAS ALONSO
PLUMBING-Rough 1/30/2025 Approved SABAS ALONSO
Underground Mechanical 1/30/2025 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 2/6/2025 Conditional Approval MICHAEL LEWIS
HVAC-Rough 2/6/2025 Corrections Issued MICHAEL LEWIS
BUILDING-Rough-Frame 2/10/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 2/10/2025 Approved ALEJANDRO DE ARTOLA
Insulation 2/10/2025 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 2/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 2/26/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/1/2025 Not Ready for Inspection BARRY HACHE
Gas Test 4/1/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Final 4/1/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 4/15/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 4/15/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 4/15/2025 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 4/15/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/30/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 4/30/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 4/30/2025 Approved ALEJANDRO DE ARTOLA
Gas Test 4/30/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 4/30/2025 Approved ALEJANDRO DE ARTOLA
Final 5/16/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 5/16/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 5/16/2025 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 5/16/2025 Approved ALEJANDRO DE ARTOLA