10745 N HELENDALE AVE 91042
Certificate Information: 10745 N HELENDALE AVE 91042
- Application / Permit
- 23010-20000-03094
- Plan Check / Job No.
- B23VN10144
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: New Detached 1-Story ADU per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 10/18/2023
- Issuing Office
- Current Status
- CofO Issued on 2/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2023 | DAVID CASTILLO |
| Corrections Issued | 8/9/2023 | DAVID CASTILLO |
| Plan Check Approved | 10/5/2023 | DAVID CASTILLO |
| Issued | 10/18/2023 | APPLICANT |
| CofO in Progress | 1/17/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 2/23/2024 | RUBEN SALAS |
| CofO Issued | 2/23/2024 | RUBEN SALAS |
| Permit Finaled | 2/23/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/9/2023 | DAVID CASTILLO |
| Address approval | Cleared | 8/19/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 8/22/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 9/19/2023 | VICTOR MENDOZA |
| Roof/Waste drainage to street | Cleared | 9/21/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/23/2023 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 10/23/2023 | Approved | WILLIAM WREN |
| Sewer | 10/23/2023 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2023 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 10/31/2023 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 11/3/2023 | Partial Approval | WILLIAM WREN |
| PLUMBING-Rough | 11/3/2023 | Partial Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 11/17/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 11/17/2023 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2023 | Approved | WILLIAM WREN |
| Green Building Rough | 11/17/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 11/17/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 11/17/2023 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 11/17/2023 | Approved | WILLIAM WREN |
| Verify Sprinkler Sign Off | 11/17/2023 | Approved | WILLIAM WREN |
| Insulation | 11/20/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 11/21/2023 | Partial Approval | WILLIAM WREN |
| Shower Pan | 11/21/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 11/22/2023 | Not Ready for Inspection | WILLIAM WREN |
| Drywall Nailing | 11/27/2023 | Approved | WILLIAM WREN |
| Green Building Rough | 11/27/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 11/27/2023 | Approved | WILLIAM WREN |
| Shower Pan | 11/27/2023 | Approved | WILLIAM WREN |
| Final | 1/5/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Gas Test | 1/5/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 1/5/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/5/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 1/5/2024 | Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/5/2024 | Approved | CHRISTOPHER ROJAS |