10745 N HELENDALE AVE 91042

Certificate Information: 10745 N HELENDALE AVE 91042

Application / Permit
23010-20000-03094
Plan Check / Job No.
B23VN10144
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: New Detached 1-Story ADU per LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 10/18/2023
Issuing Office
Current Status
CofO Issued on 2/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2023 APPLICANT
Assigned to Plan Check Engineer 8/8/2023 DAVID CASTILLO
Corrections Issued 8/9/2023 DAVID CASTILLO
Plan Check Approved 10/5/2023 DAVID CASTILLO
Issued 10/18/2023 APPLICANT
CofO in Progress 1/17/2024 CHRISTOPHER ROJAS
Permit Finaled 2/23/2024 RUBEN SALAS
CofO Issued 2/23/2024 RUBEN SALAS
Permit Finaled 2/23/2024 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/9/2023 DAVID CASTILLO
Address approval Cleared 8/19/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 8/21/2023 NIKKI ZULUETA
Sewer availability Cleared 8/22/2023 NIKKI ZULUETA
Low Impact Development (LID) Cleared 9/19/2023 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 9/21/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/23/2023 Approved WILLIAM WREN
Footing/Foundation/Slab 10/23/2023 Approved WILLIAM WREN
Sewer 10/23/2023 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/31/2023 Corrections Issued WILLIAM WREN
PLUMBING-Rough 10/31/2023 Partial Approval WILLIAM WREN
BUILDING-Rough-Frame 11/3/2023 Partial Approval WILLIAM WREN
PLUMBING-Rough 11/3/2023 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Partial Approval WILLIAM WREN
BUILDING-Rough-Frame 11/17/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 11/17/2023 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Approved WILLIAM WREN
Green Building Rough 11/17/2023 Approved WILLIAM WREN
HVAC-Rough 11/17/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 11/17/2023 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 11/17/2023 Approved WILLIAM WREN
Verify Sprinkler Sign Off 11/17/2023 Approved WILLIAM WREN
Insulation 11/20/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 11/21/2023 Partial Approval WILLIAM WREN
Shower Pan 11/21/2023 Approved WILLIAM WREN
PLUMBING-Rough 11/22/2023 Not Ready for Inspection WILLIAM WREN
Drywall Nailing 11/27/2023 Approved WILLIAM WREN
Green Building Rough 11/27/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 11/27/2023 Approved WILLIAM WREN
Shower Pan 11/27/2023 Approved WILLIAM WREN
Final 1/5/2024 OK to Issue CofO CHRISTOPHER ROJAS
Gas Test 1/5/2024 Approved CHRISTOPHER ROJAS
Green Building Final 1/5/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/5/2024 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 1/5/2024 Approved CHRISTOPHER ROJAS
Smoke Detectors 1/5/2024 Approved CHRISTOPHER ROJAS