5947 N MATILIJA AVE 91401
Certificate Information: 5947 N MATILIJA AVE 91401
- Application / Permit
- 23010-20000-03089
- Plan Check / Job No.
- B23VN10126
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 31'6" X 40' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) . WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/11/2023
- Issuing Office
- Current Status
- CofO Issued on 4/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2023 | SERGIO MUNIZ |
| Corrections Issued | 8/5/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 8/11/2023 | APPLICANT |
| Plan Check Approved | 9/11/2023 | OMAR GARNICA |
| Issued | 9/11/2023 | APPLICANT |
| CofO in Progress | 3/12/2024 | RYAN SALAZAR |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
| CofO Issued | 4/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/15/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 8/18/2023 | MEGAN GODINEZ |
| Low Impact Development (LID) | Cleared | 8/31/2023 | SERGIO MUNIZ |
| Roof/Waste drainage to street | Cleared | 9/5/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/23/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 10/23/2023 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 10/31/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 12/4/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 12/4/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 12/4/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 12/4/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 12/4/2023 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 12/4/2023 | Approved | RYAN SALAZAR |
| Insulation | 12/7/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/7/2023 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 12/14/2023 | Approved | JOHN COLEMAN |
| Shower Pan | 12/14/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Shower Pan | 12/21/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/22/2023 | Approved | RYAN SALAZAR |
| Sewer | 1/19/2024 | Approved | RYAN SALAZAR |
| Underground Mechanical | 1/19/2024 | Approved | RYAN SALAZAR |
| Final | 3/11/2024 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 3/11/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 3/11/2024 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 3/11/2024 | Approved | RYAN SALAZAR |
| Smoke Detectors | 3/11/2024 | Approved | RYAN SALAZAR |