12213 W HESBY ST 91607

Certificate Information: 12213 W HESBY ST 91607

Application / Permit
23010-20000-03085
Plan Check / Job No.
B23VN10117
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (42'-0"x52'-8"), 2993 SQFT 2-STORY SINGLE FAMILY DWELLING W/ATTACHED 2-CAR GARAGE (405 SQFT) AND FRONT COVERED PORCH (71 SQFT) W/NFPA 13D SPRINKLERS THROUGHOUT, ALL ELECTRIC BUILDING.
Permit Issued
Issued on 9/20/2024
Issuing Office
Metro
Current Status
CofO Issued on 1/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2023 APPLICANT
Assigned to Plan Check Engineer 8/10/2023 PETER MOSESIAN
Corrections Issued 8/16/2023 PETER MOSESIAN
Quality Review Completed 8/18/2023 OMID HEDAYAT
Building Plans Picked Up 8/21/2023 APPLICANT
Plan Check Approved 9/16/2024 PETER MOSESIAN
Issued 9/20/2024 APPLICANT
CofO in Progress 12/17/2025 JAVIER RAMOS JR
Permit Finaled 1/28/2026 RUBEN SALAS
CofO Issued 1/28/2026 RUBEN SALAS
Permit Finaled 1/28/2026 RUBEN SALAS

Permit Application Clearance Information

ZA Case Cleared 12/20/2023 NATHAN ROMINE
Eng Process Fee Ord 176,300 Cleared 12/21/2023 CARLOS AGUILERA
Sewer availability Cleared 12/21/2023 CARLOS AGUILERA
Specific Plan Cleared 12/26/2023 CHRISTIAN PEARSON
ZI Cleared 12/26/2023 CHRISTIAN PEARSON
ZI Cleared 12/26/2023 CHRISTIAN PEARSON
Trees in Parkway Cleared 1/19/2024 ADALBERTO VERA
Hydrant and Access approval Cleared 2/29/2024 JOHN CONNEALLY
Low Impact Development (LID) Cleared 6/25/2024 LUIS LUVANO
Permit Cleared 8/29/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 8/29/2024 CARLOS AGUILERA

Contact Information

Contractor Amin Farahpour; Lic. No.: 1079005-B 280 E FAIRVIEW AVE APT 18      GLENDALE, CA 91207
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/16/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Underground Mechanical 10/16/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/23/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 10/23/2024 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 10/24/2024 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/18/2024 Approved GAREN HAYRAPETYAN
Wood Frame 11/18/2024 Not Ready for Inspection GAREN HAYRAPETYAN
Deputy Wood Construction 12/4/2024 Conditional Approval RAUL OLAGI
Underground Mechanical 12/4/2024 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 12/24/2024 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/31/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/3/2025 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 2/12/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/12/2025 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 2/20/2025 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 2/20/2025 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 2/25/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 2/25/2025 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 2/26/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 2/26/2025 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 2/27/2025 Approved OGANES TARAKHCHYAN
Green Building Rough 2/27/2025 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 2/27/2025 Approved OGANES TARAKHCHYAN
Insulation 3/13/2025 Not Ready for Inspection KEVIN BERBERYAN
Interior/Exterior Lathing 3/13/2025 Approved KEVIN BERBERYAN
Shower Pan 3/13/2025 Corrections Issued KEVIN BERBERYAN
Insulation 3/17/2025 Corrections Issued LOUIS ESCOTO
Shower Pan 3/17/2025 Corrections Issued LOUIS ESCOTO
Drywall Nailing 3/25/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/15/2025 Approved OGANES TARAKHCHYAN
Shower Pan 4/15/2025 Approved OGANES TARAKHCHYAN
HVAC-Final 8/19/2025 Approved OGANES TARAKHCHYAN
Service/Power Release 8/19/2025 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 8/20/2025 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 8/26/2025 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Final 8/26/2025 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 8/26/2025 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Not Ready OGANES TARAKHCHYAN
Final 12/5/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Final 12/5/2025 Not Ready for Inspection WAYNE REGESTER
PLUMBING-Final 12/5/2025 Not Ready for Inspection WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 12/5/2025 SGSOV Not Ready WAYNE REGESTER
Smoke Detectors 12/5/2025 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Final 12/17/2025 Approved JAVIER RAMOS JR
Final 12/17/2025 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 12/17/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 12/17/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/17/2025 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 12/17/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 12/19/2025 Approved WAYNE REGESTER
Service/Power Release 1/26/2026 Approved JAVIER RAMOS JR