13710 W CALVERT ST 91401
Certificate Information: 13710 W CALVERT ST 91401
- Application / Permit
- 23010-20000-03083
- Plan Check / Job No.
- B23VN10108
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW SINGLE STORY FULLY ELECTRIC 37'6" x 16'8" ( 572 S.F ) ACCESSORY DWLLING UNIT PER LAMC 12.22 A.33(c) AND (d).WORK DONE PER ENGINEER DESIGN. **SEE COMMENTS.
- Permit Issued
- Issued on 10/23/2024
- Issuing Office
- Current Status
- CofO Issued on 8/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/3/2023 | JESSE ARELLANO |
| Corrections Issued | 8/4/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 8/10/2023 | APPLICANT |
| Applicant returned to address corrections | 3/26/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 5/1/2024 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 5/3/2024 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 5/13/2024 | HAYATO TSUCHIYA |
| Plan Check Approved | 5/16/2024 | MIROOSH KHACHATOORIAN |
| Issued | 10/23/2024 | APPLICANT |
| CofO in Progress | 8/25/2025 | RYAN SALAZAR |
| Permit Finaled | 8/27/2025 | RUBEN SALAS |
| CofO Issued | 8/27/2025 | RUBEN SALAS |
| Permit Finaled | 8/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/26/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 9/27/2023 | NIKKI ZULUETA |
| ZA Case | Cleared | 10/20/2023 | ALEX VELA |
| ZA Case | Cleared | 10/20/2023 | ALEX VELA |
| ZA Case | Cleared | 10/20/2023 | ALEX VELA |
| ZA Case | Cleared | 10/20/2023 | ALEX VELA |
| Hydrant and Access approval | Cleared | 11/22/2023 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2024 | BRYAN GODINEZ |
| Low Impact Development (LID) | Cleared | 3/20/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 4/12/2024 | TAL SHEMEN |
Contact Information
| Contractor | Boutique Construction; Lic. No.: 1051070-B | 21208 COSTANSO STREET #1 WOODLAND HILLS, CA 91364 |
| Engineer | Li,, Dacheng D; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/28/2024 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 11/1/2024 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 11/1/2024 | Corrections Issued | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 11/6/2024 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2024 | Partial Approval | RYAN SALAZAR |
| Non Compliance | 11/21/2024 | Not Required | RYAN SALAZAR |
| Wood Frame | 11/21/2024 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/21/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 1/21/2025 | Partial Approval | GAREN HAYRAPETYAN |
| HVAC-Rough | 1/21/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 1/21/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 1/24/2025 | Corrections Issued | RYAN SALAZAR |
| ELECTRICAL-Rough | 1/24/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 1/24/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 1/24/2025 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 1/24/2025 | Approved | RYAN SALAZAR |
| Insulation | 1/30/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 2/7/2025 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 2/14/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/14/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 2/14/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 2/18/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 3/20/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/28/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 3/28/2025 | Corrections Issued | RYAN SALAZAR |
| Final | 3/28/2025 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 3/28/2025 | Approved | RYAN SALAZAR |
| Green Building Final | 3/28/2025 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Final | 3/28/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 3/28/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 3/28/2025 | SGSOV Not Required | RYAN SALAZAR |
| Service/Power Release | 3/28/2025 | Not Required | RYAN SALAZAR |
| Smoke Detectors | 3/28/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 4/10/2025 | Approved | RYAN SALAZAR |
| Final | 4/10/2025 | Partial Approval | RYAN SALAZAR |
| Green Building Final | 4/10/2025 | Approved | RYAN SALAZAR |
| HVAC-Final | 4/10/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 4/10/2025 | Approved | RYAN SALAZAR |
| Special/Order Compliance | 4/15/2025 | Corrections Issued | RYAN SALAZAR |
| Final | 8/22/2025 | OK to Issue CofO | RYAN SALAZAR |