13710 W CALVERT ST 91401

Certificate Information: 13710 W CALVERT ST 91401

Application / Permit
23010-20000-03083
Plan Check / Job No.
B23VN10108
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED NEW SINGLE STORY FULLY ELECTRIC 37'6" x 16'8" ( 572 S.F ) ACCESSORY DWLLING UNIT PER LAMC 12.22 A.33(c) AND (d).WORK DONE PER ENGINEER DESIGN. **SEE COMMENTS.
Permit Issued
Issued on 10/23/2024
Issuing Office
Current Status
CofO Issued on 8/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2023 APPLICANT
Assigned to Plan Check Engineer 8/3/2023 JESSE ARELLANO
Corrections Issued 8/4/2023 JESSE ARELLANO
Building Plans Picked Up 8/10/2023 APPLICANT
Applicant returned to address corrections 3/26/2024 ISIS ARGUETA
Applicant returned to address corrections 5/1/2024 HAYATO TSUCHIYA
Applicant returned to address corrections 5/3/2024 MOHAMMAD ESMAILI
Applicant returned to address corrections 5/13/2024 HAYATO TSUCHIYA
Plan Check Approved 5/16/2024 MIROOSH KHACHATOORIAN
Issued 10/23/2024 APPLICANT
CofO in Progress 8/25/2025 RYAN SALAZAR
Permit Finaled 8/27/2025 RUBEN SALAS
CofO Issued 8/27/2025 RUBEN SALAS
Permit Finaled 8/27/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/26/2023 NIKKI ZULUETA
Sewer availability Cleared 9/27/2023 NIKKI ZULUETA
ZA Case Cleared 10/20/2023 ALEX VELA
ZA Case Cleared 10/20/2023 ALEX VELA
ZA Case Cleared 10/20/2023 ALEX VELA
ZA Case Cleared 10/20/2023 ALEX VELA
Hydrant and Access approval Cleared 11/22/2023 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 1/4/2024 BRYAN GODINEZ
Low Impact Development (LID) Cleared 3/20/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 4/12/2024 TAL SHEMEN

Contact Information

Contractor Boutique Construction; Lic. No.: 1051070-B 21208 COSTANSO STREET #1      WOODLAND HILLS, CA 91364
Engineer Li,, Dacheng D; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/28/2024 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 11/1/2024 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 11/1/2024 Corrections Issued RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 11/6/2024 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/21/2024 Partial Approval RYAN SALAZAR
Non Compliance 11/21/2024 Not Required RYAN SALAZAR
Wood Frame 11/21/2024 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 1/21/2025 Not Ready for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Rough 1/21/2025 Partial Approval GAREN HAYRAPETYAN
HVAC-Rough 1/21/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 1/21/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 1/24/2025 Corrections Issued RYAN SALAZAR
ELECTRICAL-Rough 1/24/2025 Approved RYAN SALAZAR
Green Building Rough 1/24/2025 Approved RYAN SALAZAR
HVAC-Rough 1/24/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 1/24/2025 Approved RYAN SALAZAR
Insulation 1/30/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 2/7/2025 Partial Approval RYAN SALAZAR
Drywall Nailing 2/14/2025 Not Ready for Inspection RYAN SALAZAR
Interior/Exterior Lathing 2/14/2025 Approved RYAN SALAZAR
Shower Pan 2/14/2025 Approved RYAN SALAZAR
Drywall Nailing 2/18/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 3/20/2025 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 3/28/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 3/28/2025 Corrections Issued RYAN SALAZAR
Final 3/28/2025 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 3/28/2025 Approved RYAN SALAZAR
Green Building Final 3/28/2025 Not Ready for Inspection RYAN SALAZAR
HVAC-Final 3/28/2025 Approved RYAN SALAZAR
PLUMBING-Final 3/28/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 3/28/2025 SGSOV Not Required RYAN SALAZAR
Service/Power Release 3/28/2025 Not Required RYAN SALAZAR
Smoke Detectors 3/28/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 4/10/2025 Approved RYAN SALAZAR
Final 4/10/2025 Partial Approval RYAN SALAZAR
Green Building Final 4/10/2025 Approved RYAN SALAZAR
HVAC-Final 4/10/2025 Approved RYAN SALAZAR
PLUMBING-Final 4/10/2025 Approved RYAN SALAZAR
Special/Order Compliance 4/15/2025 Corrections Issued RYAN SALAZAR
Final 8/22/2025 OK to Issue CofO RYAN SALAZAR