7425 N SUNNY BRAE AVE 91306

Certificate Information: 7425 N SUNNY BRAE AVE 91306

Application / Permit
23010-20000-03082
Plan Check / Job No.
B23VN10105
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-story detached ADU (33-10" x 22'-6") per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 12/14/2023
Issuing Office
Valley
Current Status
CofO in Progress on 12/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/28/2023 APPLICANT
Assigned to Plan Check Engineer 8/10/2023 VAHAN JIVALAGIAN
Corrections Issued 8/14/2023 VAHAN JIVALAGIAN
Quality Review Completed 8/16/2023 OMID HEDAYAT
Building Plans Picked Up 8/18/2023 APPLICANT
Plan Check Approved 12/14/2023 VAHAN JIVALAGIAN
Issued 12/14/2023 APPLICANT
CofO in Progress 10/23/2025 ALEXANDER HANDY
No Progress 12/17/2025 ROBERT GOLD
CofO in Progress 12/17/2025 ROBERT GOLD

Permit Application Clearance Information

Address approval Cleared 8/26/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/29/2023 COLIN LOREDO
Sewer availability Cleared 8/29/2023 COLIN LOREDO
Low Impact Development (LID) Cleared 10/24/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 10/25/2023 COLIN LOREDO
Construction near power lines Cleared 12/7/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Andrejic,, Milos; Lic. No.: C67443 3601 BEVERLY RIDGE DR      SHERMAN OAKS, CA 91423

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/23/2024 Partial Approval ALEXANDER HANDY
Footing/Foundation/Slab 2/7/2024 Not Ready for Inspection MORRIS JACKSON
Footing/Foundation/Slab 2/9/2024 Corrections Issued ALEXANDER HANDY
Special/Order Compliance 2/9/2024 Partial Inspection ARUTYUN MADATYAN
Footing/Foundation/Slab 2/13/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 5/2/2024 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 5/2/2024 Partial Approval ARUTYUN MADATYAN
HVAC-Rough 5/2/2024 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 5/2/2024 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 5/10/2024 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 5/10/2024 Corrections Issued ARUTYUN MADATYAN
Green Building Rough 5/10/2024 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Rough 5/10/2024 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 5/10/2024 Not Ready for Inspection ARUTYUN MADATYAN
Verify Sprinkler Sign Off 5/10/2024 Not Ready for Inspection ARUTYUN MADATYAN
Wood Frame 5/10/2024 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 5/29/2024 Partial Approval ARUTYUN MADATYAN
ELECTRICAL-Rough 5/29/2024 Approved ARUTYUN MADATYAN
HVAC-Rough 5/29/2024 Approved ARUTYUN MADATYAN
PLUMBING-Rough 5/29/2024 Approved ARUTYUN MADATYAN
Insulation 7/15/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 7/15/2024 Partial Approval ARUTYUN MADATYAN
Drywall Nailing 8/7/2024 Approved ARUTYUN MADATYAN
Green Building Rough 8/7/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 8/7/2024 Partial Approval ARUTYUN MADATYAN
Shower Pan 8/7/2024 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 2/28/2025 SGSOV Not Ready ALEXANDER HANDY
Special/Order Compliance 2/28/2025 Corrections Issued ALEXANDER HANDY
BUILDING-Rough-Frame 4/15/2025 Approved ALEXANDER HANDY
Final 4/15/2025 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 4/15/2025 SGSOV Not Ready ALEXANDER HANDY
Service/Power Release 4/15/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 4/28/2025 SGSOV Not Ready ALEXANDER HANDY
Final 5/6/2025 Corrections Issued ALEXANDER HANDY
Green Building Final 5/6/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 5/6/2025 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 5/6/2025 Approved ALEXANDER HANDY
Final 7/7/2025 Corrections Issued ALEXANDER HANDY
Final 8/19/2025 Not Ready for Inspection ALEXANDER HANDY
ELECTRICAL-Final 10/22/2025 Approved ALEXANDER HANDY
Final 10/22/2025 OK to Issue CofO ALEXANDER HANDY
HVAC-Final 10/22/2025 Approved ALEXANDER HANDY
PLUMBING-Final 10/22/2025 Approved ALEXANDER HANDY