7425 N SUNNY BRAE AVE 91306
Certificate Information: 7425 N SUNNY BRAE AVE 91306
- Application / Permit
- 23010-20000-03082
- Plan Check / Job No.
- B23VN10105
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story detached ADU (33-10" x 22'-6") per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 12/14/2023
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 12/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/10/2023 | VAHAN JIVALAGIAN |
| Corrections Issued | 8/14/2023 | VAHAN JIVALAGIAN |
| Quality Review Completed | 8/16/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 8/18/2023 | APPLICANT |
| Plan Check Approved | 12/14/2023 | VAHAN JIVALAGIAN |
| Issued | 12/14/2023 | APPLICANT |
| CofO in Progress | 10/23/2025 | ALEXANDER HANDY |
| No Progress | 12/17/2025 | ROBERT GOLD |
| CofO in Progress | 12/17/2025 | ROBERT GOLD |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 8/29/2023 | COLIN LOREDO |
| Low Impact Development (LID) | Cleared | 10/24/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 10/25/2023 | COLIN LOREDO |
| Construction near power lines | Cleared | 12/7/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Andrejic,, Milos; Lic. No.: C67443 | 3601 BEVERLY RIDGE DR SHERMAN OAKS, CA 91423 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/23/2024 | Partial Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 2/7/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Footing/Foundation/Slab | 2/9/2024 | Corrections Issued | ALEXANDER HANDY |
| Special/Order Compliance | 2/9/2024 | Partial Inspection | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 2/13/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 5/2/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2024 | Partial Approval | ARUTYUN MADATYAN |
| HVAC-Rough | 5/2/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 5/2/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 5/10/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Rough | 5/10/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 5/10/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 5/10/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 5/10/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Wood Frame | 5/10/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 5/29/2024 | Partial Approval | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 5/29/2024 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 5/29/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 5/29/2024 | Approved | ARUTYUN MADATYAN |
| Insulation | 7/15/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 7/15/2024 | Partial Approval | ARUTYUN MADATYAN |
| Drywall Nailing | 8/7/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 8/7/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 8/7/2024 | Partial Approval | ARUTYUN MADATYAN |
| Shower Pan | 8/7/2024 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 2/28/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Special/Order Compliance | 2/28/2025 | Corrections Issued | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 4/15/2025 | Approved | ALEXANDER HANDY |
| Final | 4/15/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 4/15/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Service/Power Release | 4/15/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 4/28/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Final | 5/6/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 5/6/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 5/6/2025 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 5/6/2025 | Approved | ALEXANDER HANDY |
| Final | 7/7/2025 | Corrections Issued | ALEXANDER HANDY |
| Final | 8/19/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Final | 10/22/2025 | Approved | ALEXANDER HANDY |
| Final | 10/22/2025 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 10/22/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 10/22/2025 | Approved | ALEXANDER HANDY |