318 1/2-3/4 W 79TH ST 90003
Certificate Information: 318 1/2-3/4 W 79TH ST 90003
- Application / Permit
- 23010-20000-03060
- Plan Check / Job No.
- B23VN10002
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. NEW 2 ACCESSORY DWELLING UNITS PER CA GOVT. CODE 65852.2(E)(1)(D) & APPLICABLE PART 2 OF LAMC 12.22 A.33(C)(D) & (G)
- Permit Issued
- Issued on 11/17/2023
- Issuing Office
- Current Status
- CofO Issued on 11/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2023 | FERNANDO FLORES |
| Corrections Issued | 8/7/2023 | FERNANDO FLORES |
| Applicant returned to address corrections | 11/8/2023 | DANIEL SANJUAN |
| Plan Check Approved | 11/17/2023 | VICTOR CHEN |
| Issued | 11/17/2023 | APPLICANT |
| CofO in Progress | 10/23/2024 | MICHAEL LEWIS |
| Permit Finaled | 11/1/2024 | DEROLD HAUFF |
| CofO Issued | 11/1/2024 | DEROLD HAUFF |
| Permit Finaled | 11/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/7/2023 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2023 | ABEL CASILLAS |
| Sewer availability | Cleared | 8/7/2023 | ABEL CASILLAS |
| Historic Resource Verification | Cleared | 8/8/2023 | MAX LODER |
| Redevelopment Project Area | Cleared | 8/11/2023 | YASMINE BASHIRI |
| Tenant Habitability Plan | Cleared | 8/14/2023 | ISMAEL HERNANDEZ |
| Hydrant and Access approval | Cleared | 9/1/2023 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 9/13/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 9/13/2023 | CHRISTINA BRACO |
| Construction near power lines | Cleared | 10/5/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/23/2024 | Partial Approval | MICHAEL LEWIS |
| Sewer | 1/23/2024 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 2/2/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 2/2/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 2/12/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 3/27/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 3/27/2024 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Rough | 3/27/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 3/29/2024 | Conditional Approval | MICHAEL LEWIS |
| Green Building Rough | 3/29/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| HVAC-Rough | 3/29/2024 | Approved | MICHAEL LEWIS |
| Insulation | 4/10/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 4/10/2024 | Approved | MICHAEL LEWIS |
| Insulation | 4/11/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 4/11/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 4/17/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 6/10/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 6/10/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 6/10/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 6/10/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 6/10/2024 | Approved | MICHAEL LEWIS |
| HVAC-Final | 6/10/2024 | Corrections Issued | MICHAEL LEWIS |
| MERV13>=Final | 6/10/2024 | Approved | MICHAEL LEWIS |
| MERV13>=Rough | 6/10/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 6/10/2024 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 6/10/2024 | SGSOV Not Required | MICHAEL LEWIS |
| Service/Power Release | 6/10/2024 | Corrections Issued | MICHAEL LEWIS |
| Smoke Detectors | 6/10/2024 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 6/10/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 6/28/2024 | Partial Approval | MICHAEL LEWIS |
| Final | 6/28/2024 | Partial Inspection | MICHAEL LEWIS |
| HVAC-Final | 6/28/2024 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Final | 6/28/2024 | Approved | MICHAEL LEWIS |
| Service/Power Release | 6/28/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Final | 7/12/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 7/12/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 7/12/2024 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 7/12/2024 | Approved | MICHAEL LEWIS |
| Service/Power Release | 7/12/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 7/18/2024 | Approved | MICHAEL LEWIS |
| Service/Power Release | 7/18/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Service/Power Release | 7/25/2024 | Approved | MICHAEL LEWIS |
| Final | 10/22/2024 | OK to Issue CofO | MICHAEL LEWIS |