1419 E 50TH ST 90011
Certificate Information: 1419 E 50TH ST 90011
- Application / Permit
- 23010-20000-03059
- Plan Check / Job No.
- B23VN09984
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NEW DETACHED ACCESSORY DWELLING UNIT WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 1/4/2024
- Issuing Office
- Current Status
- CofO Issued on 9/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2023 | KEVIN MORALES |
| Corrections Issued | 10/10/2023 | KEVIN MORALES |
| Quality Review Completed | 10/12/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 12/20/2023 | KEVIN MORALES |
| Plan Check Approved | 12/28/2023 | KEVIN MORALES |
| Issued | 1/4/2024 | APPLICANT |
| CofO in Progress | 9/26/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 9/27/2025 | DEROLD HAUFF |
| CofO Issued | 9/27/2025 | DEROLD HAUFF |
| Permit Finaled | 9/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/18/2023 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2023 | ARNULFO CHAMU |
| Sewer availability | Cleared | 10/30/2023 | ARNULFO CHAMU |
| Low Impact Development (LID) | Cleared | 12/12/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 12/12/2023 | ARNULFO CHAMU |
Contact Information
| Architect | Youssefzadeh,, Atabak; Lic. No.: NA22727 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/3/2024 | Corrections Issued | MICHAEL LEWIS |
| Sewer | 6/3/2024 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 6/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 6/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/7/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/7/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/13/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/9/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/9/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 10/10/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/15/2024 | Corrections Issued | ANTHONY RAMOS |
| Insulation | 10/15/2024 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 10/15/2024 | Partial Approval | ANTHONY RAMOS |
| Shower Pan | 10/15/2024 | Not Ready for Inspection | ANTHONY RAMOS |
| Drywall Nailing | 10/17/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 10/17/2024 | Approved | JOSH MEISTER |
| Shower Pan | 10/17/2024 | Approved | JOSH MEISTER |
| HVAC-Final | 1/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 1/23/2025 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 1/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 1/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 1/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 1/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 4/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/3/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 4/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 4/3/2025 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Service/Power Release | 4/3/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 4/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 9/24/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Service/Power Release | 9/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 9/25/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |