13170 1/2 W MERCER ST 91331

Certificate Information: 13170 1/2 W MERCER ST 91331

Application / Permit
23010-20000-03053
Plan Check / Job No.
B23VN09961
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) - PER WFPP
Permit Issued
Issued on 1/29/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2023 APPLICANT
Assigned to Plan Check Engineer 7/31/2023 JEROME MAGAT PALMA
Corrections Issued 7/31/2023 JEROME MAGAT PALMA
Building Plans Picked Up 8/30/2023 APPLICANT
Applicant returned to address corrections 1/17/2024 DANIEL ABRAMYAN
Issued 1/29/2024 APPLICANT
CofO in Progress 5/2/2025 MICHEL ABAJAN
Permit Finaled 5/15/2025 RUBEN SALAS
CofO Issued 5/15/2025 RUBEN SALAS
Permit Finaled 5/15/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/30/2023 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 8/30/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/5/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 9/21/2023 DAGOVERTO GUERRERO
Construction near power lines Cleared 1/9/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/4/2024 Partial Approval MICHEL ABAJAN
Sewer 12/4/2024 Approved MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 12/11/2024 Approved MICHEL ABAJAN
Footing/Foundation/Slab 12/11/2024 Approved MICHEL ABAJAN
Underground Mechanical 12/11/2024 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/26/2024 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 1/14/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 1/14/2025 Approved MICHEL ABAJAN
Green Building Rough 1/14/2025 Approved MICHEL ABAJAN
HVAC-Rough 1/14/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 1/14/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 1/14/2025 Approved MICHEL ABAJAN
Insulation 1/24/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/24/2025 Approved MICHEL ABAJAN
Shower Pan 1/24/2025 Approved MICHEL ABAJAN
Drywall Nailing 2/6/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 2/6/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/16/2025 SGSOV Not Required MICHEL ABAJAN
Final 4/18/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 4/18/2025 Approved MICHEL ABAJAN
Service/Power Release 4/18/2025 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 4/18/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 5/1/2025 Approved MICHEL ABAJAN
Final 5/1/2025 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 5/1/2025 Approved MICHEL ABAJAN
PLUMBING-Final 5/1/2025 Approved MICHEL ABAJAN